Lake Merced

Lake Merced in the FogScope of Work

This project includes replacing existing paths at the northwest corner of the lake from the intersection with Harding Boulevard to the Sunset Circle parking lot. A new ADA accessible, asphalt path will be installed along with an adjacent stabilized soil path, which will provide a softer surface. Additional site improvements will include installing adult fitness stations, site furnishings and replacing ADA parking spaces in the parking lot 

Funding

  • California Natural Resources Agency Grant: $1,000,000
  • 2012 Clean and Safe Neighborhood Parks Bond Citywide Parks Program: $2,000,000
  • 2012 Clean and Safe Neighborhood Parks Bond - Forestry Program: $1,000,000
  • 2018 Parks Bond Act - Recreational Infrastructure Revenue Enhancement: $634,540

Total Sources: $4,634,540

Project Schedule

PhaseTimeline
PlanningFall 2017
DesignWinter 2021
Phase I, Construction
Late 2023
Phase I, Open to the public
Early 2024
Phase II, Construction
Spring through Fall 2024
Phase II, Open to the publicLate 2024


Project Updates

If you would like to sign-up for Project Update blog posts like the ones below, click here, scroll down to the News Flash section, and then select "RPD Park Improvements | All Project Updates" to receive updates on all our active projects, or pick-and-choose your blog subscriptions by project name. You’ll receive an email that includes a link to confirm your new subscription for each blog for which you sign-up.

  1. Project Update Blog
  2. Documents and Materials
  1. Capital Project Update

    Lake Merced | Construction update, November 2023

    Construction is going smoothly on the improvements near John Muir Parking Lot. The contractor has installed the concrete pad for the Read on...
  2. Capital Project Update

    Lake Merced Project update | March 2023

    As a quick update, the upcoming Lake Merced project, which involves renovation of the pathways on the north side of the lake, is undergoing preparation to take construction bids Read on...
  3. Capital Project Update

    Lake Merced Project Preparing Bid Documents!

    We are happy to report that the project team is in the process of preparing for . . . Read on...
  4. Capital Project Update

    Lake Merced Joint City Agency Project Updates Meeting February 17th!

    Please join Recreation and Parks, the Public Utilities Commission (PUC), and the Municipal Transportation Authority (MTA) for a . . . Read on...
  5. Capital Project Update
  6. Capital Project Update

    TEMPORARY WALKWAY CLOSURE AT LAKE MERCED FEB 2020

    Trees will be removed as part of the trail and restroom project at Lake Merced beginning Monday, February 17, 2020 Read on...
  1. Alexis Ward