Golden Gate Park - Botanical Garden Bookstore Barrier Removal Project
Completed and Opened to the public October 2024!
Scope of Work
This project designed and constructed a ramp and handrails to ensure that the Botanical Garden Bookstore complies with the Americans with Disabilities Act (ADA).
Background
In late 2021, Recreation and Park Department staff received a citizen complaint about access into the bookstore because it had one step up into the facility and no handrail or ramp. RPD’s ADA Coordinator for Physical Access and staff from the Mayor’s Office on Disability performed a site visit and confirmed the site conditions. Staff adopted a programmatic solution to accommodate patrons until the ramp and handrails could be completed.
Funding
Funding for the current scope of work will be allocated from RPD’s annual set-aside for ADA improvement projects.
Project Schedule
| Phase | Timeline |
| Planning | May 2023 |
| Design | Summer 2023 |
| Construction begins | mid-2024 |
| Open to the public | October 2024 |
Project Updates
If you would like to sign-up for Project Update blog posts like the ones below, click here, scroll down to the News Flash section, and then select "RPD Park Improvements | All Project Updates" to receive updates on all our active projects, or pick-and-choose your blog subscriptions by project name. You’ll receive an email that includes a link to confirm your new subscription for each blog for which you sign-up.
Get Out and Play!
Thanks for supporting park improvements in your San Francisco parks! To stay informed and involved, we encourage you to subscribe to Rec and Park eNews.
You can also explore Rec and Park volunteer opportunities – We have park needs in every corner of the city and volunteer opportunities that are as diverse as your interests, skills, and abilities. Have fun in your parks, and get out and play!
-
-
Golden Gate Park - JFK Promenade | Construction advisory, February 9, 2026
Please be advised that most of Conservatory Drive East will be closed to pedestrians and cyclists for road work Tuesday, Feb. 10 through Friday, Feb. 13. This closure may resume the following week, if needed. There will be orange road barricades and Read on... -
Golden Gate Park - JFK Promenade | Construction update, February 2026
Please be advised that curb work started this week at Pompeii Circle in front of the Conservatory of Flowers. JFK Promenade will remain open to pedestrians throughout construction, and pedestrians and cyclists will be directed around the Read on... -
Community Opportunity Fund (COF) | First important deadline is next Tuesday, February 3
Nominations are open for Rec and Park’s Community Opportunity Fund, a program that supports community-driven park improvement projects across the city. The first deadline is approaching, and attendance at one of two February workshops is a required Read on... -
Kezar Pavilion Renovation Project | Project update, January 2026
We are excited to share that we will be releasing a Release for Qualifications/Proposals (RFQP) for a Construction Manager/General Contractor (CMGC) for the Kezar Pavilion Renovation Project in early 2026! This will allow us to integrate the Read on... -
Community Opportunity Fund (COF) | Nominations for projects are now open!
Nominations for Community Opportunity Fund (COF) projects are now open! To get started today: Visit the program page, review the sample application, application instructions, scoresheet, FAQs, and the Implementation Plan! Sign up for a Read on... -
Golden Gate Park - JFK Promenade | Construction update, January 2026
Construction to upgrade the crosswalks and curb ramps on JFK Promenade near the Conservatory of Flowers resumes this week. Our contractor will begin at Conservatory Drive East before turning attention to the intersection at Pompeii Circle. All crosswalk Read on... -
Golden Gate Park-Senior Center Outdoor Recreation Area | Project update, December 2025
Thank you to everyone who joined us for our third and final community meeting about the planned improvements to create a new Outdoor Recreation Area behind the Golden Gate Park Senior Center. Our plan is to present this concept design to the Read on... -
Golden Gate Park-Senior Center Outdoor Recreation Area | REMINDER: Community meeting #3, Dec 17, 11a
Join Rec and Park for the third and final community meeting about the planned improvements to create a new Outdoor Recreation Area behind the Golden Gate Park Senior Center. At this meeting, we will share the final design for the new Outdoor Recreation Read on... -
Golden Gate Park-Senior Center Outdoor Recreation Area | REMINDER: Community meeting #3, Dec 17, 11a
Join Rec and Park for the third and final community meeting about the planned improvements to create a new Outdoor Recreation Area behind the Golden Gate Park Senior Center. At this meeting, we will share the final design for the new Outdoor Recreation Read on... -
Golden Gate Park - JFK Promenade | Construction update, December 2025
Construction to upgrade the crosswalks and curb ramps on JFK Promenade near the Conservatory of Flowers has begun! Our contractor is working to remove and replace the crosswalks and curb ramps at Pompeii Circle and Conservatory Drive East. This work is Read on... -
Golden Gate Park-Senior Center Outdoor Recreation Area | Community meeting #3, Dec. 17, 11a
Join Rec and Park for the third and final community meeting about the planned improvements to create a new Outdoor Recreation Area behind the Golden Gate Park Senior Center. At this meeting, we will share the final design for the new Outdoor Recreation Read on... -
Golden Gate Park - Botanical Garden Access Improvements | Construction update, November 2025
The ADA Pathway Improvement Project at San Francisco Botanical Garden is now complete! All designated ADA-compliant paths are now complete and open to the public. Thank you for your support throughout construction. This will be our Read on... -
Golden Gate Park | Construction begins soon on JFK Promenade near Stanyan Street
We are excited to announce that construction will begin next week to upgrade crosswalks and curb ramps on JFK Promenade near Stanyan Street. JFK Promenade will remain open to pedestrians throughout construction. Expect construction noise, intermittent Read on... -
Golden Gate Park - Botanical Garden Access Improvements | Construction update, October 2025
This month, extensive demolition and re-grading continue along select pathways around the Fountain Plaza, Mediterranean Garden, Rhododendron Garden (east of the Waterfowl Pond), New Zealand and South African Gardens. These areas are expected to reopen to Read on... -
Golden Gate Park - Botanical Garden Access Improvements | Construction update, September 26, 2025
With this year’s Flower Piano now finished, construction resumed this week with the start of Phase 3. This part of the project will include demolishing and repaving asphalt pathways near the Moon Viewing Garden, Southeast Asian Cloud Forest, and Read on... -
Golden Gate Park - Botanical Garden Access Improvements | Construction update, September 2025
We’re excited to report that the Friend Gate (North Gate) is now open again! Work around the Friend Gate was Phase 2 of this project and included construction of new stairways and ramps, pathway paving work, and installation metal handrails around the Read on... -
Golden Gate Park | Construction begins soon on Stanyan Street Sidewalk Improvements
We are excited to announce that the Stanyan Street Sidewalk Improvements Project will be starting construction soon. This project will upgrade existing sidewalks and driveway aprons at the parking lot entrances on the west side of Stanyan between Read on... -
Golden Gate Park - Botanical Garden Access Improvements | Construction update, August 2025
Phase 1 of the project is now complete and open to the public! Phase 1 involved pathway improvements in the southeast section of the gardens (Mesoamerican Cloud Forest), including paving work and installation of concrete ramps and metal handrails. This is Read on... -
Golden Gate Park - Botanical Garden Access Improvements | REMINDER: North Gate Closed, Use Main Gate
Construction Advisory: Please be advised that the Friend Gate (North Entrance) will close for over a month beginning Monday, July 21, 2025. Please use Main Gate entrance at 9th Avenue. This work at the Friend Gate is “Phase 2” of the Read on... -
Golden Gate Park - Botanical Garden Access Improvements | Construction update, July 2025
Construction Advisory: Please be advised that the Friend Gate (North Entrance) will close for over a month beginning Monday, July 21, 2025. Please use Main Gate entrance at 9th Avenue. This work at the Friend Gate is “Phase 2” of the Read on... -
Golden Gate Park - Bay Area Young Survivors (BAYS) Memorial Garden | Construction update, May 2025
The Golden Gate Park - BAYS Breast Cancer Memorial Garden project is now complete. Thank you for your support throughout construction. This will be our last blog update for this project. Please visit our park improvements webpage to learn about Read on... -
Mayor Lurie, Breast Cancer Survivors Unveil Nation’s First Permanent Breast Cancer Memorial Garden
Golden Gate Park’s First New Memorial in More Than 30 Years Honors Lives Lost to Breast Cancer, Offers Place of Healing for All. Read on... -
Golden Gate Park | Traffic Improvements Near Music Concourse in Golden Gate Park Begin May 12
Rec and Park, in partnership with the San Francisco Municipal Transportation Agency (SFMTA), is making roadway and curb changes in Golden Gate Park along northbound Martin Luther King Jr. Drive, near Shakespeare Garden, to improve traffic flow and Read on... -
Kezar Pavilion Renovation Project | Concept Design approved by Rec & Park Commission
Thank you to everyone who supported the concept design for the renovation of Kezar Pavilion. The Recreation and Park Commissioners unanimously approved the design yesterday! Our next step is to work on the Read on... -
Kezar Pavilion Renovation Project | REMINDER: Concept Design review at Rec Park Commission, April 17
On April 17, Rec & Park staff will be presenting the concept design for the Kezar Pavilion Renovation Project to the Recreation and Park Commission for approval. This marks an important milestone for the project, and we want to thank everyone for their Read on... -
Kezar Pavilion Renovation Project | UPDATE: Concept Design review moved to April Commission meeting
MEETING UPDATE: The Kezar Pavilion Concept Design agenda item was moved to the Recreation and Park Commission meetings in April. In April, RPD staff will be presenting the concept design for the Kezar Pavilion Renovation Project to the Read on... -
Kezar Pavilion Renovation Project | UPDATE: Concept Design review moved to April Commission meeting
MEETING UPDATE: The Kezar Pavilion Concept Design agenda item was moved to the Recreation and Park Commission meetings in April. In April, RPD staff will be presenting the concept design for the Kezar Pavilion Renovation Project to the Read on... -
Kezar Pavilion Renovation Project | Project update, January 2024
MEETING UPDATE: The Kezar Pavilion Concept Design agenda item was moved to the Recreation and Park Commission meetings in April. In April, RPD staff will be presenting the concept design for the Kezar Pavilion Renovation Project to the Read on... -
Golden Gate Park-Senior Center Outdoor Recreation Area | REMINDER: Survey #2 open through January 13
Based on feedback from the initial round of community outreach, two concept designs have been created to illustrate a range of potential alternatives. The NEW OUTDOOR RECREATION AREA will enable us to support more senior-focused outdoor fitness Read on... -
Kezar Pavilion Renovation Project | Project update, December 2024
Thanks to everyone who attended our third community meeting on December 16, where we explored the final concept design for this legendary venue. The meeting materials, including the presentation and meeting boards, are now posted on the project webpage Read on... -
Golden Gate Park-Senior Center Outdoor Recreation Area | Survey #2 open now through January 13
Based on feedback from the initial round of community outreach, two concept designs have been created to illustrate a range of potential alternatives. The NEW OUTDOOR RECREATION AREA will enable us to support more senior-focused outdoor fitness Read on... -
Kezar Pavilion Renovation Project | REMINDER: Community Meeting on Monday, December 16, 6:00-7:30 pm
Join us to explore the final concept design for this legendary venue. In addition, staff from San Francisco Arts Commission will share exciting, new opportunities for public art at Kezar and staff from Department of Emergency Management will offer Read on... -
Golden Gate Park - 9th and Lincoln Gateway | Construction complete
The 9th & Lincoln Gateway Improvements are complete. Thank you for your support throughout construction. This will be our last blog update for this project. Please visit our park improvements webpage to learn about other major projects happening in the Read on... -
Let’sPlaySF! Initiative | Take the Let'sPlaySF! Playground Survey open through January 31, 2025
Thanks to the successful Let’sPlaySF! Initiative funded by the 2012 Park Bond, SF Parks Alliance, and philanthropic partners we are renovating 13 dilapidated playgrounds across our city. With 11 playgrounds already beautifully renovated and two more Read on... -
Kezar Pavilion Renovation Project | Community Meeting on Monday, December 16, 6:00-7:30 pm
Join us to explore the final concept design for this legendary venue. In addition, staff from San Francisco Arts Commission will share exciting, new opportunities for public art at Kezar and staff from Department of Emergency Management will offer Read on... -
Golden Gate Park-Senior Center Outdoor Recreation Area | Community meeting #2, Dec. 12, 3-4p
Through the funding support of the 2020 Parks Bond and the Board of Supervisors, Rec and Park is conducting outreach and actively engaging with the community for a new Outdoor Recreation Area, near the existing GGP Senior Center. This space will enable us Read on... -
Kezar Pavilion Renovation Project | Project update, November 2024
We are planning for a community meeting in the coming weeks to share the final schematic design and to discuss the public art program. We will be sharing the date and time soon Read on... -
Mayor Breed Joins Inner Sunset Community to Celebrate Improved 9th & Lincoln Gateway
The $3 million renovation project, the latest in a series of enhancements to make the park more welcoming, accessible, and safe for all visitors, links Golden Gate Park to the bustling Irving Street commercial corridor Read on... -
Kezar Pavilion Renovation Project | Project update, October 2024
This month, the project team presented the design of Kezar Pavilion at Civic Design Review for a Phase I concept design. We are happy to report that the design was approved and we can proceed with the project. We are anticipating hosting a final Read on... -
Golden Gate Park - 9th and Lincoln Gateway | Ribbon cutting ceremony, November 1, 11 AM to 12:30 PM
Join us for the reopening of the 9th & Lincoln Gateway in Golden Gate Park! Ribbon cutting ceremony followed by a reception at the Thomas Church Pavilion Celebration Garden at the San Francisco Botanical Garden. Read on... -
Golden Gate Park - San Francisco Botanical Garden Bookstore | Construction is now complete!
We are excited to announce that the accessibility improvement project at the beloved Botanical Garden Bookstore is now complete. This project installed a ramp and handrails to ensure compliance with the Americans with Disabilities Act (ADA) Read on... -
Kezar Pavilion Renovation Project | Project update, September 2024
Thanks to everyone who attended our community open house in Golden Gate Park! We received lots of great feedback and heard from folks interesting in native plants, programming for youth and seniors and a desire to create a welcoming and active plaza space Read on... -
Golden Gate Park-Senior Center Outdoor Recreation Area | DATE CHANGE: Community meeting Oct 9, 4:30p
RESCHEDULED: Community meeting is now on October 9, 4:30-5:30 pm. No meeting on October 2. Join us to learn more about this project, talk to Rec and Park staff, see the results of the initial survey, and offer your feedback on the design of this exciting Read on... -
Golden Gate Park - San Francisco Botanical Garden Bookstore | Construction update, September 2024
Construction began on July 17 and the construction of the new ADA deck and ramp is moving forward nicely. The new decking work is now complete, and the contractor is finishing the custom steel handrails which will be installed in the next two weeks Read on... -
Golden Gate Park - Bay Area Young Survivors (BAYS) Memorial Garden | Construction Begins!
This month, Rec and Park joined Bay Area Young Survivors (BAYS) to break ground on the BAYS Breast Cancer Memorial Garden in Golden Gate Park. Once complete, the revitalized garden area will serve as a space for reflection, honoring the many people who Read on... -
Golden Gate Park - Middle Lake | Construction is complete!
Middle Lake is now open! Thank you for your support throughout construction. This will be our last blog update for this project. Be sure to check out our two brand-new audio tours of Middle Lake which provide interesting historical and ecological context Read on... -
Kezar Pavilion Renovation Project | Reminder! Community Meeting on Saturday, August 24, 10:30-noon
Reminder! We hope to see you next weekend in Golden Gate Park for a community open house to discuss the Kezar Pavilion Renovation Project. We will be sharing updated design drawings and seeking your feedback on the architecture, the outdoor plaza design Read on... -
Golden Gate Park - Senior Center Outdoor Recreation Area | Survey extended through September 15
Take the survey! Now extended through Sunday, September 15. Through the funding support of the 2020 Parks Bond and the Board of Supervisors, Rec and Park is beginning the early outreach and community engagement phase for a new Outdoor Recreation Area Read on... -
Kezar Pavilion Renovation Project | Civic Design Review Committee on Monday, August 19, 2pm
The project team will be presenting updated designs for the renovation of Kezar Pavilion to the San Francisco Civic Design Review Committee on Monday, August 19th at 2pm. The meetings are held in hybrid format and open to the public Read on... -
Golden Gate Park - 9th and Lincoln Gateway | Construction update, August 2024
If you've been through the intersection lately, you'll notice that the team has made good progress – stone walls are complete, paving on both sides of the intersection has been poured, and all new pathways will soon be open to pedestrians. In the coming Read on... -
Golden Gate Park - Senior Center Outdoor Recreation Area | Community Feedback Requested!
Through the funding support of the 2020 Parks Bond and the Board of Supervisors, Rec and Park is beginning the early outreach and community engagement phase for a new Outdoor Recreation Area, near the existing GGP Senior Center. Read on... -
Golden Gate Park - Middle Lake | Environmental Restoration Creates Hub for Wildlife & People
San Francisco Recreation and Park Department officials this week celebrated new improvements completed at Golden Gate Park’s Middle Lake, resulting in nearly 2 acres of glistening water where a dry lakebed and invasive species stood for decades. Read on... -
Golden Gate Park - San Francisco Botanical Garden Bookstore | Construction update, July 2024
Construction began on July 17 and the construction of the new ADA deck and ramp is moving forward nicely. The new decking is being installed now and once this is complete, the contractor will install the new handrails and curb railing. The project is Read on... -
Golden Gate Park - Bay Area Young Survivors (BAYS) Memorial Garden | Project update, July 2024
Construction on the Bay Area Young Survivors (BAYS) Memorial Garden is now slated to begin Fall 2024. Expect to see minor impacts around Arguello Blvd and Conservatory Drive East/West. If any closures or detours are required, we will post notifications. Read on... -
Kezar Pavilion Renovation Project | Community Meeting on Saturday, August 24, 10:30-noon
We are planning for a community outreach event on Saturday, August 24, 10:30-noon to get feedback on the renovation design of Kezar Pavilion and input on future programming. We will be hosting an open house style workshop outdoors in Read on... -
Golden Gate Park - 9th and Lincoln Gateway | Construction update, June 2024
The walls and paving on the west side have been completed. That side of the gateway is now open to pedestrians. The contractor is now hard at work on the stone masonry walls on the east side of the intersection. The masonry work should be complete within Read on... -
Golden Gate Park - Kezar Pavilion Renovation | Project update, June 2024
We have completed environmental review on the Kezar Pavilion Renovation Project. This is an important step that all of our capital renovation must go through. We have re-engaged with our design team to continue Read on... -
Golden Gate Park - Middle Lake | Construction update, June 2024
The project is almost finished – Paving work is nearly complete, and we are taking steps to help ensure that all our newly planted plants become healthy and well-established. Construction fences will remain up around the project perimeter until the Read on... -
Golden Gate Park - Kezar Pavilion Renovation | Project update, May 2024
We are continuing many of the tasks from last month including finalizing a cost estimate, completing environmental review and performing additional on-site survey work. We are hoping to Read on... -
Golden Gate Park - 9th and Lincoln Gateway | Construction update, May 2024
Construction has begun on the west side of the intersection, and everything has been going smoothly. Footings for the light poles have been installed, two new traffic lights have been erected, and progress on the masonry planter walls has Read on... -
Golden Gate Park - Middle Lake | Construction update, May 2024
The taps at Middle Lake are now open and the cascade is flowing! If you’ve been by the lake recently, you may have noticed that the lake is now full, receiving water from Read on... -
Golden Gate Park - Kezar Pavilion Renovation | Project update, April 2024
Our project team is continuing to work hard on moving forward the design of the Kezar Pavilion Renovation Project. We are currently getting cost estimates performed for the construction work so that we can refine our Read on... -
Golden Gate Park - Bay Area Young Survivors (BAYS) Memorial Garden | Project updates April 2024
BAYS will be looking to secure a General Contractor for the project by the end of next month. Construction is slated to begin late Summer 2024 Read on... -
Golden Gate Park - Kezar Pavilion Renovation | Project update, March 2024
Thank you to everyone who was able to attend our community meeting on March 12! We had more than 30 people participate and offer feedback on the project and designs. Big thanks to Public Works architects for their Read on... -
Golden Gate Park - Middle Lake | Construction update March 2024
We are excited to announce that we are scheduled to begin filling Middle Lake on Tuesday, March 19. Over the next days and weeks, the lake will gradually be filled to the top. The water to fill the lake will enter from the Read on... -
Golden Gate Park - San Francisco Botanical Garden Bookstore | Project update March 2024
As we announced in January, we put out a call for construction bids for this project. The bid process closed, and we are pleased to announce that NBC Construction is the Read on... -
Golden Gate Park - Kezar Pavilion Renovation Project | REMINDER! Community Meeting March 12, 6 PM
REMINDER! Community meeting Tuesday, March 12, 6 to 7:30 PM. SF Rec & Park, in partnership with the Department of Emergency Management, will be renovating Kezar Pavilion to accommodate enhanced recreational activities and to function as Read on... -
Golden Gate Park Golf Course Clubhouse project | Project complete! Clubhouse now open!
The Golf Course Clubhouse in Golden Gate Park is now open! You can read our press release here and check out some of our favorite photos Read on... -
Golden Gate Park - Kezar Pavilion Renovation Project | Community Meeting Tuesday, March 12 6 to 7:30
SF Rec & Park, in partnership with the Department of Emergency Management, will be renovating Kezar Pavilion to accommodate enhanced recreational activities and to function as a disaster response facility in the event of Read on... -
Golden Gate Park Golf Course Clubhouse | Reopening on February 16!
Join us for the reopening of the Golden Gate Park Golf Clubhouse on Friday, February 16 at 11 a.m. This event will celebrate the brand new clubhouse with a Read on... -
Golden Gate Park - Bay Area Young Survivors (BAYS) Memorial Garden | Super Stroll and Roll, Feb. 11
On February 11, join the Bay Area Young Survivors and the Bay Area Ridge Trail in the trail's 9th annual Super Stroll and Roll, a free event to walk and ride through San Francisco's streets and trails. This year, the event will begin at Read on... -
Golden Gate Park - San Francisco Botanical Garden Bookstore | Project out to bid
SF Botanical Garden Bookstore Barrier Removal Project is out to bid! Bids are due on February 7, 2024 at 2:30 pm PDT. Read on... -
Golden Gate Park - Golf Clubhouse project | Construction update January 2024
The construction of the Golf Clubhouse is getting closer to completion! For the building exterior, windows and doors are now fully installed at the building, and the contractor is finishing up the installation of the siding. Inside, there is Read on... -
Golden Gate Park - 9th and Lincoln Gateway | Project update January 2024
We anticipate that construction will begin this month on 9th Avenue and Lincoln Way in Golden Gate Park. Expect to see fencing and construction equipment being staged onsite in the coming weeks. Soon after Read on... -
Golden Gate Park - Middle Lake | Construction update January 2024
We have some exciting progress to report since our last update at the end of November. Due to the rains, the lake has begun to refill with water. This has given us the opportunity to observe the new lake liner in action. The lake liner is Read on... -
Golden Gate Park - San Francisco Botanical Garden Bookstore | Project update January 2024
We received the permit from the Department of Building Inspection and the project is getting prepared to go out to bid. Rec & Park will be performing work on a new accessible ramp and deck at the Read on... -
Golden Gate Park - Golf Clubhouse project | Construction update December 2023
Construction on the Golf Clubhouse experienced delays this fall related to supply chain issues that slowed down the delivery of some necessary building materials. This has pushed back our expected completion date for the project to February 2024 Read on... -
Golden Gate Park - 9th and Lincoln Gateway | Project update Nov-Dec 2023
We anticipate that construction will begin in January on 9th Avenue and Lincoln Way in Golden Gate Park. No construction is planned for December 2023. The construction contract commenced in Read on... -
Golden Gate Park - Middle Lake | Construction update Nov-Dec 2023
Construction is moving swiftly at Middle Lake. Much of the soils are prepped and the contractor has begun laying out planting. You will start to see Read on... -
JFK Promenade | Construction work now complete! (street striping removal)
We have completed the removal of outdated street striping (painted lines) from portions of JFK Promenade from Kezar Drive to Transverse Drive. Check out the video Read on... -
Starting Tomorrow: JFK Promenade | Construction Advisory for November 20-22
Starting tomorrow, Monday, November 20th, Rec and Park will be removing outdated street striping (painted lines) from portions of JFK Promenade from Kezar Drive to Transverse Drive. Read on... -
JFK Promenade | Construction Advisory, November 2023
Rec and Park will be removing outdated street striping (painted lines) from portions of JFK Promenade from Kezar Drive to Transverse Drive. Construction to grind off this street striping will take place in Read on... -
Golden Gate Park - Bay Area Young Survivors (BAYS) Memorial Garden | Project updates November 2023
We’re excited to report that the design of the BAYS Memorial Garden is now complete. BAYS is currently in the process of Read on... -
Golden Gate Park - Middle Lake | Construction update October 2023
Both lake islands have been constructed and the lake grading and clay liner are now almost complete! Our contractor also recently completed a pipe repair and pipe extension at the south end of Read on... -
Golden Gate Park - Golf Clubhouse project | Construction update October 2023
The construction is moving right along. Earlier this fall, we experienced some supply chain delays that lengthened the duration of the project and Read on... -
Golden Gate Park - 9th and Lincoln Gateway | Project update October 2023
Construction will begin soon on 9th Avenue and Lincoln Way in Golden Gate Park. We designed the project to be completed in two phases (east and west corners) to minimize Read on... -
Golden Gate Park - San Francisco Botanical Garden Bookstore | Project update October 2023
Rec and Park is working on the design of a ramp and deck at the San Francisco Botanical Garden Bookstore in Golden Gate Park to ensure it complies with Read on... -
Golden Gate Park - Stow Lake Perimeter Path Renovation | All paths open! Project now complete!
The Stow Lake Perimeter Path Renovation project is now complete! All paths around the lake are now open. Work for this project included Read on... -
Bay Area Young Survivors (BAYS) Memorial Garden | Project updates September 2023
Inspired by the success of the beautiful AIDS Memorial Grove in Golden Gate Park as an example of both a public amenity and a dedicated memorial space, Bay Area Young Survivors (BAYS) inquired Read on... -
Golden Gate Park - 9th and Lincoln Gateway | Project update September 2023
Very soon, construction will begin at the gateway to Golden Gate Park at 9th Avenue and Lincoln Way, one of the most Read on... -
Golden Gate Park - Middle Lake | Construction update, August 30, 2023
Construction at Middle Lake in Golden Gate Park took a brief break during August to make room for Outside Lands but the project is now back up and running! Next steps are Read on... -
Golden Gate Park - Golf Clubhouse | construction update August 2023
The construction of the Golf Clubhouse is progressing nicely. Our contractor has been working on installing all of the Read on... -
Golden Gate Park - San Francisco Botanical Garden Bookstore
Rec and Park will be performing construction work to ensure that the Botanical Garden Bookstore complies with required building codes and the Americans with Disabilities Act Read on... -
Golden Gate Park - 9th and Lincoln Gateway | Project update July 2023
On July 20, our Rec and Park Commission unanimously approved a contract award to Bauman Landscape and Construction for project work that we believe will greatly improve and revitalize Golden Gate Park's 9th Avenue Gateway Read on... -
Golden Gate Park - Middle Lake | Project update July 2023
In preparation for Outside Lands, the contractor will be demobilizing and taking a break for three weeks starting next Monday, July 31. Construction will be in full swing again by September. Read on... -
Golden Gate Park - BAYS Memorial Garden | Project update July 2023
The BAYS Memorial Garden is wrapping up the design phase, having received approval of the concept design from the Read on... -
Stow Lake Perimeter Path | Construction update July 2023
The repaving work at Stow Lake continues to be moving along very well. We have completed 75% of our Read on... -
Golden Gate Park - Golf Clubhouse construction update | July 2023
Construction of the Golf Course Clubhouse is moving right along. Over the next few weeks, the contractor will be Read on... -
Golden Gate Park - Middle Lake | Project update June 2023
The rehabilitation work at Middle Lake continues. The scope of this project includes recontouring the lake bottom, installing a clay Read on... -
Golden Gate Park - Middle Lake | Project update May 2023
Middle Lake Rehabilitation is moving along quickly! Rough grading of the lake and cascade is nearly complete Read on... -
Waller Street Skate Park Project | Project Complete! Now open!
Waller Street Skate Park project is complete! The park is now open and we hope you get out there and enjoy it! Check out these photos from Read on... -
Golden Gate Park - Golf Clubhouse construction update | March 2023
We're happy to report that the Golden Gate Park Golf Clubhouse project has received its building permit and construction is underway Read on... -
Golden Gate Park – 9th and Lincoln Gateway Project Update | March 2023
The 9th Avenue Gateway is moving forward and is scheduled to be Read on... -
Golden Gate Park – 9th and Lincoln Gateway Project Update | March 2023
The 9th Avenue Gateway is moving forward and is scheduled to be Read on... -
Golden Gate Bandshell Welcomes Back More Live Performances in 2023
Diverse lineup to play 100+ free concerts at historic landmark venue Read on... -
Waller Street Skate Park Project Construction Update 9/19!
2 inches of fine asphalt was laid during the last week of August. . . Read on... -
Lisa and Douglas Goldman Tennis Center will open on March 3rd!
Wednesday, March 3, 2021, the Lisa and Douglas Goldman Tennis Center will open to the public. Read on... -
GGP Dog Training Area December Update
The historic Dog Training Area is very close to completion, however project opening has been delayed until late January. We have had some December delays due to the COVID-19 pandemic... Read on... -
Golden Gate Park Tennis Center December Update
The Tennis Center is making great progress towards completion in early 2021. The courts are now fully color coated, fences are installed, and planting is nearing completion. Read on... -
Construction wrapping up at the GGP Dog Training Area!
We are in the final phases of construction at the historic Golden Gate Park Dog Training Area . . . Read on... -
Golden Gate Park Tennis Center Project Update 11/4!
Check out the great article on the project . . . Read on... -
Golden Gate Park Stanyan Edge Project Update 10/7!
Wanted to give a quick update on the this project. . . Read on... -
Golden Gate Park Tennis Center Project Update 10/7!
The Tennis Center construction continues to move forward with finishes and technology . . . Read on... -
Construction is Completed for the Stanyan Street Edge of Golden Gate Park!
If you haven’t noticed yet, all the construction fencing has been removed on the project that the public should have full access to the east edge of the park. . . Read on... -
GGP Dog Training Area: Construction Underway!
Construction is underway at the Golden Gate Park Dog Training Area! Read on... -
GGP Tennis Center Construction Update June 2020
The Tennis Center construction is moving along on schedule and despite some delays due to COVID-19 the Tennis Center is still on track for a late fall opening. Read on... -
Golden Gate Park Tennis Center Construction Update 5/13!
The Tennis Center construction team continues to move forward with construction . . . Read on... -
Construction continues on Stanyan Edge Project
After a months long pause on our project, we have finally given the green light for the contractor to begin work again. Read on... -
Construction at the Golden Gate Park Dog Training Area Starting Soon!
I hope you are well and finding opportunities to connect with nature and virtually connect with community during this time of sheltering in place. Read on... -
SF REC AND PARK COMMISSION GREENLIGHTS OPERATOR OF GOLDEN GATE PARK TENNIS CENTER
Lifetime Activities, a company that runs municipal tennis centers in five Bay Area cities, has been chosen to operate the Golden Gate Park Tennis Center Read on... -
GGP DOG TRAINING AREA – TREE WORK COMPLETE
Tree maintenance and removals are now complete at the Golden Gate Park Dog Training Area Read on... -
-
GGP DOG TRAINING AREA – TEMPORARY CLOSURE WEEK OF 10/28
Please be advised that the Golden Gate Park Dog Training Area will be fully closed from Monday, October 28 through Wednesday, October 30 for tree pruning and removals Read on... -
OAK WOODLANDS TRAILS PROJECT TEAM WINS AWARD- SEP 2019
Last week, the Golden Gate Park Oak Woodlands Trails Improvement Project team, comprised of staff from Rec and Park and Public Works as well as the contractor, Yerba Buena Engineering & Construction, Inc, was honored with an award for partnering Read on... -
GGP DOG TRAINING AREA PROJECT UPDATE
The design team is putting the finishing touches on the construction drawings for the renovation of the Dog Training Area Read on... -
-
SF Rec and Parks Breaks Ground on $27M Tennis Center
Tennis enthusiasts of all ages gathered today with City officials, the Tennis Coalition of San Francisco, and the San Francisco Parks Alliance to celebrate a new era for public tennis Read on... -
OAK WOODLANDS PROJECT UPDATE- JAN 2019
Here are a few updates on the Golden Gate Park Oak Woodlands Trails Improvement Project Read on... -