Hello neighbors! Construction at Middle Lake in Golden Gate Park took a brief break during August to make room for Outside Lands but the project is now back up and running!
Next steps are grading and construction of the second island, planting around the lake perimeter, finishing the cascade below the casting ponds, and building out the bridges on the east side of the lake.
We are still on target to finish construction and open up the trails around the lake by January 2024, and we look forward to welcoming you back then!
For more information, see the project website >>
Alex Schuknecht, Project Manager, alex.schuknecht@sfgov.org