Background
The Fillmore Turk Mini Park community, under the new name of New Community Leadership Foundation, initiated improvements when they received a Community Opportunity Fund (COF) award of $330,000 for the park. COF is a program of the 2012 Clean and Safe Neighborhood Parks Bond. In 2019, Supervisor Brown committed $100,000 from the General Fund towards the project. In 2020, SF Beautiful received a Community Challenge Grant award of $100,000. With additional funding from 2012 Clean and Safe Neighborhood Parks Bond, General Fund, Open Space Funds and pro-bono design services from TS Studio, Landscape Architects this project budget is just over one million dollars.
Scope of Work
This 2012 Bond Community Opportunity Fund (COF) Project at Fillmore Turk Mini Park will revitalize the park with new landscaping, drainage, seating within the park.
Funding
Total project budget is just over one million dollars, including:
- Community Opportunity Fund (COF) award, 2012 Clean and Safe Neighborhood Parks Bond: $330,000
- General Fund: $100,000
- SF Beautiful Community Challenge Grant award: $100,000
- Pro-bono design services from TS Studio, Landscape Architects
Project Schedule
Phase | Timeline |
Planning | Fall 2018 |
Design | Summer 2019 |
Construction | Fall 2022 - Late Summer 2023 |
Open to the public | Late Summer 2023 |
Project Updates
If you would like to sign up for updates click here and scroll down to the NewsFlash and select the alerts you would like to receive.
-
-
Fillmore Turk Construction Groundbreaking, CANCELLED!
Fillmore Turk Renovation starts 12/12/22 . . . Read on... -
Fillmore Turk Mini Park Update- 10/05/22
We are excited to report that the construction contractor is currently being certified after receiving Commission approval to award . . . Read on... -
Fillmore Turk Mini Park Project Update 04/26/22
The contractor asked to be relieved from the construction contract and in February, Commission approved the termination so that we can . . . Read on... -
Fillmore Turk Mini Park Project Update 12/2021
Say goodbye to 2021 and the drainage problems at Fillmore Turk— Read on... -
Fillmore Turk Mini Park Project Update 11/23/21
We are awarding the construction contract in December!! . . . Read on... -
Fillmore Turk Mini Park Project Update 11/2021
The construction contract is being awarded in November 2021 and . . . Read on... -
Fillmore Turk Mini Park Project Update 9/2021
We received seven bids in June and Public Works contracting administration is in the final stages of identifying the lowest responsive and responsible bidder. . . Read on... -
Fillmore Turk Mini Park Project Update 3/29/21
Target bid advertisement will be mid-Spring 2021. . . Read on... -
Fillmore Turk Mini Park Project Update 1/29/21
We just received notice that the building permit has been approved! Read on... -
Fillmore/Turk Mini Park Project Update 10/13!
So much to report! Read on... -
FILLMORE TURK MINI PARK – OCTOBER 2019
Exciting News! Late September, Recreation and Park Commission approved design for Fillmore Turk Mini Park. Read on... -
Fillmore Turk Mini Park Community Meeting
Join the New Community Leadership Foundation and San Francisco Beautiful to review the scope of work, schedule and budget Read on...
Project Details
- Fillmore Turk Mini Park - Concept Design, September 4,2019 (PDF)
- Fillmore Turk Mini Park - CEQA, September 4, 2019 (PDF)
- Fillmore Turk Mini Park - Preservation Team Review, September 4, 2019 (PDF)
Commission Materials
- Rec Park Commission staff report, September 19, 2019 (PDF)
- Rec Park Commission staff report - donor recognition plan, September 4, 2019 (PDF)
- Rec Park Commission staff report - donor recognition plan, May 14, 2019 (PDF)
Community Meetings - Notes and Presentations
- N/A
-
Marien Coss
Project ManagerPhone: 1-628-652-6647
-
Eoanna Harrison Goodwin
Project ManagerPhone: (628) 652-6645