Background

Noe Valley Town Square (NVTS) is located at 3861 24th Street (between Sanchez and Vicksburg Streets) on the 24th Street commercial corridor. The site is .25 acres and is surrounded by a mix of retail shops and services, restaurants, and multi-family and single-family residences. The property was purchased by RPD in June 2013 and the concept design was approved by the Recreation and Park Commission in 2014. The proposal to establish a public open space at the site evolved through more than four years of collaboration between the Department the community group Residents for Noe Valley Town Square, then-Supervisor Scott Wiener’s office, and the San Francisco Parks Alliance. NVTS opened to the public in October 2016.

The approved 2014 concept plan contemplated a public restroom in the northeast corner of the plaza. Due to funding constraints at that time, the restroom element was removed from the project. Since then, the Department allocated funds in the FY 21-22 budget for project planning including evaluating the viability of a modular restroom at the site and preparing cost estimates for project funding. Before that work began, the Noe Valley community successfully advocated for State funds for the project. Their ask was based on a high-level budget estimate for a custom-built restroom at the site.   

In November 2022, the Department was approached by Vaughan Buckley with Volumetric Building Companies and Chad Kaufman with Public Restroom Company, who expressed interest in contributing a prefabricated modular restroom to Noe Valley Town Square.    

In addition, RPD will hire an as-needed landscape design firm to supplement the donor’s design drawing package. These drawings will include all work associated with site improvements. These plans include demolition, grading, paving, fencing, irrigation and landscape. RPD drawings will include the donor drawings which detail the restroom building and all associated mechanical, electrical and plumbing work. 

The addition of a restroom to Noe Valley Town Square has been approved by the Planning Department and found to be consistent with the project’s categorical exemption under CEQA. The Civic Design Committee has determined that this project would be reviewed under their administrative process. The Recreation and Park Commission approved the acceptable of the restroom and site improvement gift in February 2023 and the Board of Supervisors will review the gift acceptance in March 2023.

Scope of Work

The addition of a modular single-user all-gender accessible restroom at Noe Valley Town Square, site improvements, landscaping, and beautification. 

Funding

  • In-kind Grant Funding
  • City Funding
  • State Grant (pending)

Project Schedule

PhaseTimeline
PlanningJanuary - March 2023
DesignApril - May 2023
Bid/AwardJune - July 2023
Construction beginsFall 2023
Open to the publicEnd of 2023


Project Updates

If you would like to sign-up for Project Update blog posts like the ones below, click here, scroll down to the News Flash section, and then select "RPD Park Improvements | All Project Updates" to receive updates on all our active projects, or pick-and-choose your blog subscriptions by project name. You’ll receive an email that includes a link to confirm your new subscription for each blog for which you sign-up.

  1. Project Update Blog
  2. Documents and Materials
  1. Capital Project Update

    Noe Valley Town Square Restroom | Project update October 2023

    We have received the building permit from the San Francisco Department of Building Inspection and we are working with our restroom donors to bring on contractors to Read on...
  2. Capital Project Update

    Noe Valley Town Square Restroom | Project update August 2023

    Since our last update, the design plans for the new restroom were approved by the State of California. With this approval, we can now Read on...
  3. Capital Project Update

    Noe Valley Town Square Restroom | Project update May 2023

    We’re happy to report that at the end of last month the donor gift of a prefabricated modular restroom was approved by the Board of Supervisors and Civic Design Review Read on...
  4. Capital Project Update

    Noe Valley Town Square Restroom Project Update

    The project will go to the Board of Supervisors at the end of Read on...