McLaren Park - Herz Recreation Center Project

Completed and Opened to the Public on January 9, 2026!

 

Scope of WorkAerial Rendering of what the Rec Center will look like, this is a drawing illustrating those plans.

The opening of the new Herz Recreation Center made it the first Recreation Center built from the ground up in San Francisco in more than 25 years.

The new facility delivers a modern, multifunctional recreation hub to the area, welcoming residents from the Sunnydale and Visitacion Valley neighborhoods.

Spanning 11,500 square feet, the facility features a full-size basketball court with bleacher seating for 200 people; a multipurpose room for community rentals and wellness classes; a welcoming lobby and reception area; staff offices; restrooms; a kitchen; and ample storage space—creating a flexible space designed to serve residents of all ages.

Background

The Recreation and Park Department partnered with the HOPE SF Team, including Mercy Housing and Related CA, to construct a new recreation center/gymnasium at Herz Playground, a site within John McLaren Park. 

The new recreation center was designed and built to fit cohesively within the existing park landscape and “the Hub,” a new community center campus with childcare services and recreational facilities. The vision for the overall Hub is to be an inclusive, safe, friendly, family and youth focused place for neighborhood residents and visitors.

Funding

The project combines funding from federal, city, and private funds as follows:

  • 2020 Health & Recovery Bond: $10,000,000
  • 2020 Health & Recovery Bond, Sustainability Program: $4,000,000
  • Sunnydale LLC Grant: $10,000,000
  • General Fund Capital Baseline: $600,000
  • Federal Appropriation:  $1,500,000

Total Sources: $26,100,000

The construction contract award for this project was approved by Recreation and Parks Commission on June 15, 2023 (PDF). This construction contract award obtained and complies with all city, state, and federal regulatory approvals, including any that are specific to this project's funding sources. 

Estimated Project Schedule

PhaseTimeline
PlanningWinter 2019
DesignSpring 2021
Construction contract awardedJune 15, 2023
Construction begins
Fall 2023
Open to the publicJanuary 9, 2026


Project Updates

If you would like to receive updates about the McLaren Park - Herz Recreation Center Project, please visit the News Flash section of our webpage and subscribe to "Rec Park Improvements: McLaren Park - Herz Recreation Center." To receive updates about all our active projects, subscribe to "Rec Park Improvements | All Project Updates."

  1. Project Updates
  2. Documents and Materials
  1. Project Update

    State-of-the-art Herz Rec Center Opens with Community Celebration

    San Francisco’s first new recreation center in more than two decades brings modern amenities and new opportunities to Herz Playground. Read on...
  2. Project Update

    Herz Recreation Center | Grand Opening Celebration, this Friday, January 9, 3:30-5 PM

    We’re excited to invite the community to celebrate the grand opening of the new Herz Recreation Center at 160 Mrs. Jackson Way in McLaren Park on Friday, January 9, from 3:30–5:00 p.m. The new recreation center includes an indoor basketball court with Read on...
  3. Capital Project Update

    Herz Recreation Center | Construction update, September 2025

    We’re getting close! The gym is nearly finished, all the outdoor fitness equipment has been installed, and we’re focused now on some of the final activities needed to complete the project, including installing furnishings, surfacing near the Read on...
  4. Capital Project Update

    Herz Recreation Center | Construction update, June 2025

    Exciting progress continues at Herz Recreation Center! Inside the recreation center, the space is coming together beautifully. Many of the interior finishes are complete, including sleek tilework in the restrooms, new cabinetry for the office and Read on...
  5. Capital Project Update

    Herz Recreation Center | Construction update, April 2025

    Construction is progressing well at the Herz Recreation Center. Utilities are being tied in, basketball hoops have been installed, and both interior and exterior finishes are underway. These finishings will continue in the coming months. We anticipate Read on...
  6. Capital Project Update

    Herz Recreation Center | Build Your Future with CityBuild Academy!

    Rec Park is proud to collaborate with CityBuild and the Office of Economic and Workforce Development to support workforce development. These partnerships have enabled us to engage local laborers, who are currently making an impact at Herz Rec Center. Read on...
  7. Capital Project Update

    Let’sPlaySF! Initiative | Take the Let'sPlaySF! Playground Survey open through January 31, 2025

    Thanks to the successful Let’sPlaySF! Initiative funded by the 2012 Park Bond, SF Parks Alliance, and philanthropic partners we are renovating 13 dilapidated playgrounds across our city. With 11 playgrounds already beautifully renovated and two more Read on...
  8. Capital Project Update

    McLaren Park | McLaren Park Collaborative meeting, November 18, 6:30 pm

    Rec and Park staff will share various capital project updates at the virtual McLaren Collaborative meeting this evening, Monday 11/18, starting at 6:30 pm Read on...
  9. Capital Project Update

    Herz Recreation Center | Construction update, October 2024

    This month, we enjoyed celebrating the opening of the Sunnydale Community Center along with our partners from Mercy Housing, Related California, Boys & Girls Club, and Wu Yee Children's Services Read on...
  10. Capital Project Update

    Herz Recreation Center | Construction update, September 2024

    We are making good progress on building Herz Rec! The overall structure of the building is in place and the contractor is working on the exterior wall assemblies and the roof. They are also continuing to grade the overall site Read on...
  11. Capital Project Update

    Herz Recreation Center | Construction update, August 2024

    Herz Recreation Center is starting to take shape! The building’s slab is in place and the contractor is now working on the exterior walls Read on...
  12. Capital Project Update

    Herz Recreation Center | Construction update, July 2024

    We are making exciting progress on the new Herz Recreation Center. The contractor recently installed cross laminated timber elements and glulam beams. They will be pouring the building’s foundation next and performing additional site grading. Read on...
  13. Capital Project Update

    Herz Recreation Center | Construction update, June 2024

    Construction is moving along at the new Herz Recreation Center! The steel columns are in place and the building is starting to take shape. We are looking forward to having our cross laminated timber elements installed starting next week. Read on...
  14. Capital Project Update

    Herz Recreation Center | Construction update May 2024

    Check out these recent photos of the on-going activities at Herz Playground. The building’s walls are starting to go up! Read on...
  15. Capital Project Update

    Herz Recreation Center | Construction update April 2024

    The project site has been busy as our contractor has poured the building’s concrete footings, and they are working on constructing the walls and Read on...
  16. Capital Project Update

    Herz Recreation Center | Construction update March 2024

    Since our last update in January, we installed rebar, are building a mock-up for a portion of the exterior of the building, and the contractor will soon begin pouring the building’s concrete footings. We’ll keep Read on...
  17. Capital Project Update

    Herz Recreation Center | Construction update January 2024

    Since our last update in November, demolition, excavation, and site work has wrapped up. Contractors are now working on preparing the footings for the future building structure Read on...
  18. Capital Project Update

    Herz Recreation Center | Construction update November 2023

    Since our last construction update in October, our contractors have completed surveying the site and installing all the necessary tree protection measures. This month, we will Read on...
  19. Capital Project Update

    Herz Recreation Center | Project update October 2023

    Exciting news to share. We broke ground this month on Herz Recreation Center, an all-new facility set to open in early 2025, located at Read on...
  20. Capital Project Update

    Herz Playground Now Open! | Project update September 2023

    Thank you to all of the community members who attended the ribbon cutting ceremony, including our speakers: Mayor London Breed, District 10 Supervisor Shamann Walton Read on...
  21. Capital Project Update

    Herz Playground Now Open! | Community, City Officials Celebrate $3.38 Million Makeover

    Creative new play equipment for kids of all ages and a park makeover inspired by nature greeted families at the renovated Herz Playground in McLaren Park Read on...
  22. Capital Project Update

    Herz Playground | Reopening Celebration, August 24!

    Join us to celebrate the renovation and reopening of Herz Playground on August 24 Read on...
  23. Capital Project Update

    Herz Rec Center | Project update August 2023

    On June 15, our Rec and Park Commission unanimously approved a contract award to SJ Amoroso Construction Co., LLC. to construct the new Herz Rec Center Read on...
  24. Capital Project Update

    Complete the McLaren Park 2020 Bond Planning priorities survey

    We’ve created a new map-based survey to collect your thoughts on possible programming, infrastructure, and connectivity improvements in John McLaren Park. Please take 15-20 minutes Read on...
  25. Capital Project Update

    Herz Playground | Project update June 2023

    We are rounding the corner on progress with Herz Playgound and the space is really taking shape! The play equipment is Read on...
  26. Capital Project Update

    Herz Rec Center | Project update May 2023

    Bids from contractors for the construction of Herz Recreation Center opened on May 17. Rec and Park is now reviewing the bids we have Read on...
  27. Capital Project Update

    Herz Recreation Center Project update | Bids open May 17

    Earlier this month, we held a pre-bid meeting on-site to review the scope of the Herz Recreation Center Project with potential bidders. We are looking forward to opening bids on May 17th. As a reminder, the bid information can be found Read on...
  28. Capital Project Update

    Herz Recreation Center Project update | April 2023

    Herz Recreation Center is out to bid! Bids are due on Read on...
  29. Capital Project Update

    SF Rec and Park Commission Meeting at Joe Lee Rec Center | March 16 at 10 a.m.

    Come meet your Rec and Park Commissioners at our offsite Commission meeting at Joe Lee Rec Center Read on...
  30. Capital Project Update

    Herz Recreation Center Project update | February 2023

    We are finalizing our bid set of documents for the Herz Recreation Center Project... Read on...
  31. Capital Project Update

    Recreation Center Project Update 1/20!

    Hi everyone, We are thrilled to share that we obtained our building permit for the Herz Recreation Center Project! Read on...
  32. Capital Project Update

    Herz Rec Project Update 12/20/22

    Hi folks, We enjoyed celebrating a joint groundbreaking for the new Community Center with our project partners . . . Read on...
  33. Herz Rec GB

    San Francisco Breaks Ground on New Community & Recreation Center at Sunnydale Hope SF

    Sunnydale Community Hub will provide safe and accessible space for sports, recreation, cultural events, health and wellness resources, and educational programs and activities. Read on...
  34. Capital Project Update

    Herz Recreation Center Update 10/26/22

    Hi all- We are excited to share that the children’s playground at Herz is now in construction! . . . Read on...
  35. Capital Project Update

    Herz Rec Construction Update 9/16!

    Hi everyone- We are making steady progress on having our construction documents reviewed by the Department of Building Inspection and other City agencies. . . Read on...
  36. Capital Project Update

    Herz Recreation Center Update 8/24!

    Hi all- We are closing to wrapping up the permitting review through the Department of Building Inspection! Read on...
  37. Capital Project Update

    Sanjay Vora selected for the Herz Rec Center Public Art Piece!

    We are thrilled to share that Sanjay Vora has been selected as the artist for the . . . Read on...
  38. Capital Project Update

    Art finalists for Herz Rec Center!

    Hi all- Thank you to those who provided input the proposed artwork for the Herz Recreation Center. . . Read on...
  39. Capital Project Update

    Herz Recreation Center Update 5/20!

    Hi all- Thank you to those who provided input the proposed artwork for the Herz Recreation Center. . . . Read on...
  40. Capital Project Update

    Herz Rec Art Proposals on Display, View them at Coffman Pool.

    The Herz Recreation Center Artist Selection Panel has selected three artists to create proposals for . . . Read on...
  41. Capital Project Update

    Herz Rec Center Project Update March 2022

    The project team and Rec Park staff continue to finalize details in the design of the new Rec Center and outdoor spaces Read on...

Contact Us

Eoanna Harrison Goodwin

Project Manager