Construction is moving full steam ahead across all five blocks of the park!
- Sewer work is nearly complete, and electrical conduit and light pole footing installation begins this week.
- Irrigation mainline installation is underway, led by a Black-owned LBE plumbing subcontractor brought on by McGuire and Hester.
- Structural footing installation for more Memory Walk art fencing will begin next week.
- Sidewalk and street work impacts: the project will soon begin to install piping for the park’s green infrastructure. Expect occasional parking restrictions and pedestrian detours. Please follow posted signs and flagger directions.
Workforce Highlights:
- A third hyperlocal laborer starts this week, sponsored by contractor McGuire and Hester.
- Are you a journey-level operating engineer? Interested in working on the project? Contact La'Kista Coleman at lcoleman@successcenters.org.
Training Opportunity: Success Centers’ next construction pre-apprentice training cohort starts November 3. Orientation is required, with sessions available on October 28 and October 30. For details, check the attached flyer or contact Derrie at dmcclure@successcenters.org or 415-575-0423.
๐ฌ Have questions or concerns?
Feel free to contact the project manager:
Lauren Dietrich Chavez
๐ 628-652-6643
Please visit the project webpage at:
Buchanan Street Mall Renovation Project