We’ve made solid progress since our last construction update in April.
Demolition and utility work are currently underway. Storm drainage work is moving forward. We’re also managing our orders of materials with long-lead times, such as ADA signage and glass doors, to keep the project on track.
We're still on pace to complete construction in early 2026, followed by a few finishing touches.
๐ฌ Have questions or concerns?
Feel free to contact the project manager:
Alex Schuknecht
๐ง alex.schuknecht@sfgov.org
๐ 628-652-6631
South Sunset Clubhouse Renovation