Hi all- This will be our last blog update for the project. The park is open and we hope you all are enjoying it! We are wrapping up a small amount of finishing touches on-site and we are completing all the paperwork to official close the project. Thanks again for all your support and patience with us to make this park a reality! For questions please contact Project Manager, Alexis Ward, at alexis.ward@sfgov.org
Rec Park Improvements: Guy Place Mini Park
Posted on August 21, 2020
-
Hi everyone- We are officially open! Thank you to all the community members and City staff that have helped make this project a reality! We hope you can get out and enjoy the park.
Thank you and take care!
Rec Park Improvements: Guy Place Mini Park
Posted on July 27, 2020
-
Hi everyone-
The contractor on Guy Place Mini Park has been busy finalizing details on-site such as installing wire mesh around the columns and installing planter railings. Work will be complete very soon and we appreciate everyone’s support and patience with us as wrap up construction on this new park! For questions please contact Project Manager, Alexis Ward, at alexis.ward@sfgov.org.
Rec Park Improvements: Guy Place Mini Park
Posted on May 22, 2020
-
Please see the photograph of the artist fence and the metal columns that have been installed at Guy Place Mini Park. For questions please contact Project Manager, Alexis Ward, alexis.ward@sfgov.org.
Rec Park Improvements: Guy Place Mini Park
Posted on May 01, 2020
-
Hi all-
Work on public projects such as Guy Place will continue at this time. The contractor has been focusing on installing the pavers and cobbles at the site.
We hope everyone is safe and healthy.
Rec Park Improvements: Guy Place Mini Park
Posted on March 23, 2020
-
Hi everyone- Earlier this week, the contractor installed the new sidewalk in front of the park. Please note that this weekend, the contractor is planning to work on Saturday, Feb. 22 in order to lay out the new pavers inside the park. We apologize for any inconvenience.
Rec Park Improvements: Guy Place Mini Park
Posted on February 21, 2020
-
Thank you to Sup. Haney and neighbors for organizing the community meeting in early February. FYI on traffic impacts:
The contractor for Guy Place Park, may need to close a portion of the road in front of the park on Wednesday, February 19, from 10:00am-3:00pm. They will be pouring in the new sidewalk in front of the park. People beyond the park sidewalk will be able to exit in their vehicles.
Rec Park Improvements: Guy Place Mini Park
Posted on February 19, 2020
-
Hi everyone-
We are making some good progress on-site and the contractor has installed the granite stone, which is a focal point in the new park. We are also busy planting trees and working on the new irrigation system. Next steps will include installing the metal columns and placing the boulders on-site.
For any questions or concerns please reach out to Alexis.Ward@sfgov.org.
Thanks!
Alexis
Rec Park Improvements: Guy Place Mini Park
Posted on February 06, 2020
-
Construction progress has been intermittent over the past few weeks due to a unexpected conflict with street utilities in the area of the new bulb out. This issue affects both the Guy Place Mini Park project as well as the streetscape project, managed by San Francisco Public Works. Both project teams are working with PG&E to resolve this issue as quickly as possible. A normal pace of construction is anticipated to resume soon. Thank you for your patience and understanding.
By: Brett Desmarais
Rec Park Improvements: Guy Place Mini Park
Posted on November 15, 2019
-
A new sidewalk bulb-out (a widened area of sidewalk) is under construction in front of Guy Place Mini Park. The bulb-out will feature a new pet relief area with permeable paving and a pet drinking fountain.
By: Brett Desmarais
Rec Park Improvements: Guy Place Mini Park
Posted on October 23, 2019
-
A fourteen foot slab of granite arrived at Guy Place Mini Park this week. The contractor is currently preparing to install it in the rear corner of the park where it will serve as an ornamental focal point to the space. Granite paving and boulders as well as trees will be installed soon, so please stay tuned!
San Francisco Public Works also recently began a sewer replacement project on First Street that will extend to Guy Place and Lansing Streets. Thank you for your patience throughout these construction projects. We are looking forward to completing the park and opening it to the community later this year.