Golden Gate Park - 9th and Lincoln Gateway | Construction update, June 2024

Rec Park Improvements | All Project Updates Posted on June 28, 2024

Since our last update in May, we’re excited to share our progress on the 9th & Lincoln Gateway Improvements project.

The walls and paving on the west side have been completed. That side of the gateway is now open to pedestrians.

The contractor is now hard at work on the stone masonry walls on the east side of the intersection. The masonry work should be complete within the next few weeks, and once it is done, we’ll pour the paving and commence with landscape planting.

We’re expecting to have the project completed by the end of the summer. Stay tuned for an announcement of the official opening date!

For more information, please visit the project webpage >>

If you have any questions, please feel free to reach out.

Alex Schuknecht, Project Manager, alex.schuknecht@sfgov.org