McLaren Park Group Picnic and Playground Construction Update 3/24

Rec Park Improvements | All Project Updates Posted on March 24, 2020

Hi all,  work on public projects such as this one is continuing at this time. The contractor has recently installed the sod and completed installing utilities for the new restroom along John F. Shelley Drive. The focus will mostly be on restroom work and landscaping at this time.  We aim to re-open Shelley Dr once stockpiled soil can be removed from the site. 

On the left hand side are newly installed picnic tables, seat wall and concrete work. On the left is

In the foreground is the newly installed lawn area. In the background is the picnic area showing a p

We hope everyone is safe and healthy. 