News Flash

Posted on: November 30, 2023

Golden Gate Park - 9th and Lincoln Gateway | Project update Nov-Dec 2023

Capital Project Update

Hello neighbors! We anticipate that construction will begin in January on 9th Avenue and Lincoln Way in Golden Gate Park. No construction is planned for December 2023.

The construction contract commenced in November and now the contractor is preparing the ...

Read on...

Additional Info... RPD Park Improvements: Golden Gate Park - 9th & Lincoln Gateway
Posted on: October 6, 2023

Golden Gate Park - 9th and Lincoln Gateway | Project update October 2023

Capital Project Update

Hello neighbors! As we shared in our September update, construction will begin soon on 9th Avenue and Lincoln Way in Golden Gate Park.

We designed the project to be completed in two phases (east and west corners) to minimize disturbance during construction...

Read on...

Additional Info... RPD Park Improvements: Golden Gate Park - 9th & Lincoln Gateway
Posted on: September 21, 2023

Golden Gate Park - 9th and Lincoln Gateway | Project update September 2023

Capital Project Update

Hello neighbors! The gateway to Golden Gate Park at 9th Avenue and Lincoln Way is one of the most well used park entrances by pedestrians, cyclists, and drivers. Very soon, construction will begin on landscape and wayfinding improvements that will create ...

Read on...

Additional Info... RPD Park Improvements: Golden Gate Park - 9th & Lincoln Gateway
Posted on: July 25, 2023

Golden Gate Park - 9th and Lincoln Gateway | Project update July 2023

Capital Project Update

We have great news to share. On July 20, our Rec and Park Commission unanimously approved a contract award to Bauman Landscape and Construction for project work that we believe will greatly improve and revitalize Golden Gate Park's 9th Avenue Gateway. Com...

Read on...

Additional Info... RPD Park Improvements: Golden Gate Park - 9th & Lincoln Gateway
Posted on: March 7, 2023

Golden Gate Park – 9th and Lincoln Gateway Project Update | March 2023

Capital Project Update

The 9th Avenue Gateway is moving forward and is scheduled to be

The 9th Avenue Gateway is moving forward and is scheduled to be advertised for bids in April! If the city receives acceptable bids, we can expect the project to break ground in early summer for an estimated eight month construction timeline. Traffic and t...

Read on...

Additional Info... RPD Park Improvements: Golden Gate Park - 9th & Lincoln Gateway
Posted on: September 7, 2022

Golden Gate Park – 9th and Lincoln Gateway Project Update September 2022!

Capital Project Update

The design team is closing in on 100% completion of the construction documents and the project will soon be advertised for bids. . .

The design team is closing in on 100% completion of the construction documents and the project will soon be advertised for bids. The project is on track to begin construction in early 2023 for an 8 month construction duration. Rec and Parks will coordinat...

Read on...

Additional Info... RPD Park Improvements: Golden Gate Park - 9th & Lincoln Gateway
Posted on: August 20, 2021

Golden Gate Park - 9th and Lincoln Gateway Project Update 8/20!

Capital Project Update

As this project neared 60% design completion it was put on hold due to COVID related funding delays . . .

As this project neared 60% design completion it was put on hold due to COVID related funding delays – but we are back up and running! With new funding allocated to the project the design team is moving forward and we hope to put the project out ...

Read on...

Additional Info... RPD Park Improvements: Golden Gate Park - 9th & Lincoln Gateway