MCLAREN PLAYGROUND & RESTROOM PROJECT UPDATE FEB 2020

Rec Park Improvements | All Project Updates Posted on February 21, 2020

Hi everyone! Work is continuing on-site with the installation of the new pathways which connect to the playground and the picnic areas. The contractor is currently installing the swings in the playground and next week they will begin to trench down John F. Shelley Drive to bring utilities down to the new restroom. A portion of the road will be closed during this time. We hope to have it re-opened by the end of March.

Alexis Ward, Project Manager