South Park Traffic Calming Improvements – Update Jan 2018

Two of the three South Park bulb-outs are done!

The third bulb out (on the northwest corner) will be completed late January/early February, pending adverse weather. You’ll notice the engineers confirming the structural substrate for accessible crosswalk are compliant prior to the concrete pour this month.

The remaining tasks are:

Street asphalt stamping, February 2018-

Once the sidewalks have been completely cured, the contractor will install the asphalt brick pattern immediately adjacent to the future crosswalks. The overall installation takes several weeks; however, the contractor will segment the work to minimize disturbance to through traffic.

Crosswalk Striping, March 2018

Once the work above is completed, SFMTA will paint the curbs, install crosswalks and post remaining traffic restriction signs.