First Portion of Improved Oak Woodlands Trail Open for Use in Golden Gate Park

Happy to report that the first section of new trail (of many sections!) is open for use in the Oak Woodlands of Golden Gate Park.  If you would like to try it out, please click here with that area called out in white bubble, with note.  Trailside restoration / erosion … Continue reading

First Golden Gate Park Oak Woodlands Trail Section to Open Soon!

Our contractor is making steady progress with the Golden Gate Park Oak Woodlands Trail Improvement Project. A previous update here covered the fact that restoration and construction work would occur in stages throughout the Oak Woodlands, that individual trail segments would be closed during work, and that the overall trail … Continue reading

Road Closures East End of Golden Gate Park for Oak Woodlands Trails Improvement Project

Please be advised of the following road closures in Golden Gate Park this week and next week: Wednesday, August 15 and Thursday, August 16, 8 am through 4 pm:  Arguello between Fulton and Conservatory Drive and Conservatory Drive West entrance closed: Parking will still be available along Conservatory Drive (accessed from Conservatory … Continue reading

Progress with Oak Woodlands Trails Improvements

Our contractor is making good progress with improvements to the trails in the special Oak Woodlands area of Golden Gate Park. Trail realignment work and hazardous tree removal work has started at the western edge of the Oak Woodlands. Trail surfacing work will begin the week of July 23. The … Continue reading

Site Work Starting June 25 on Oak Woodlands Trails Improvement Project

Just a heads up that on-site work will be beginning in the Golden Gate Park Oak Woodlands on Monday, June 25. Restoration and construction work will occur in stages throughout the Oak Woodlands. Individual trail segments will be closed during work. However, the overall trail network will remain mostly open … Continue reading

Oak Woodlands Trail Improvement Project Construction Starting Soon in Golden Gate Park

Rec and Park has issued NTP (Notice to Proceed) to Yerba Buena Engineering & Construction, Inc. for this coming Tuesday, June 5, which starts the clock on the construction contract, which will include work until early 2019. Restoration and construction work will occur in stages throughout the Oak Woodlands. Individual … Continue reading

Golden Gate Park Oak Woodlands Trail Improvements Coming Soon

Rec and Park received 2 bids from contractors for the Golden Gate Park Oak Woodlands Trail Improvement Project. The apparent low bidder is Yerba Buena Engineering & Construction, Inc. Pending final review of bid and confirmation that it is responsive, construction contract award will be presented to the Recreation and … Continue reading

GGP Oak Woodlands Trails Improvement Project Out to Bid

The Golden Gate Park Oak Woodlands Trails Improvement Project has been advertised to contractors. Pre-bid conference and site walk was held on March 6.  Bids are due on March 22.  We are hoping to present construction contract award to the Rec and Park Commission in April and start construction in … Continue reading

Oak Woodlands Trails Improvement Project Schedule

The target timeline that we posted late last year was to complete construction documents and advertise to contractors sometime this summer.  Please see updated anticipated project schedule below.  The largest reason for the updated timeline is that our landscape architect was unexpectedly out on leave for several months; however, there … Continue reading

Site Visit and Survey of Green Waste Transfer Area for Oak Woodlands Trails Project

You may wonder- what does the green waste transfer area along Conservatory Drive have to do with the Oak Woodlands Trails Improvement Project?  Because we are planning a trail that runs along the north edge of this zone, we want to make sure to separate the utility area with the … Continue reading

Golden Gate Park Oak Woodlands Trails Improvement Project Progress

The originally scoped budget for the Oak Woodlands Trails Improvement Project, as part of the 2008 Bond, was $300,000, with additional support from a Coca‐Cola Bottling Company grant for $94,859.  We’ve learned a great deal about construction methods and cost from previously completed trails projects.  Our trails team has revisited … Continue reading

Natural Areas Program at Oak Woodlands

A snapshot of the SFRPD Natural Areas Program staff and volunteers taking care of some of the oldest Coastal Live Oak trees in the city of San Francisco at the Oak Woodlands, an extraordinary remnant of native landscape in the northeast corner of Golden Gate Park. Come join the fun … Continue reading

Oak Woodlands Trail Improvement Project: Hazardous Tree Mitigation Work to Proceed Fall 2013

[This photo shows a dead tree standing, one of the hazardous trees slated for removal] Pending approval by the Rec and Park Commission in September, we will begin the hazardous tree mitigation component of the Oak Woodlands Trails Improvement Project this Fall. The Trails Improvement Project is the result of … Continue reading

Oak Woodlands Trail Update

The Oak Woodland Trail Restoration project is moving forward. On September 15th the Recreation and Park Commission approved the Oak Woodland Trail concept plan that was developed with input from community members.  The project will now begin the design development phase and is anticipated to begin construction in 2012. Oak Woodlands Trail concept … Continue reading

OAK WOODLANDS TRAILS COMMUNITY MEETINGS

The Recreation and Park Department is hosting a series of community meetings to  discuss future trail restoration improvements to the Oak Woodlands Trail in Golden Gate Park.  Your input is important and will help us improve the Oak Woodlands Trail in a way that is most beneficial to the community. The meeting … Continue reading