Alvord Lake Tunnel Repair Project Update
Despite the rainy winter, the contractors are putting the finishing touches on the bridge repair patches and plan to be complete by the end of April. The bridge looks fantastic.
Despite the rainy winter, the contractors are putting the finishing touches on the bridge repair patches and plan to be complete by the end of April. The bridge looks fantastic.
The repair of Alvord Lake Bridge is in full swing with the failing wall now reset in place and the pouring of the concrete retaining wall behind it taking place today. The westbound sidewalk along Kezar Drive on the south side of the bridge is now closed as the … Continue reading
The construction contract for this project has been awarded to Giampolini Courtney, a firm with extensive experience in historic concrete repair work. Work will begin in November 2018 and the construction duration is 5 months.