Description
Synthetic turf was installed at the Youngblood Coleman soccer field over ten years ago. This field is at the end of its useful life and is in need of replacement.
Scope of Work
Replace turf, turf infill, and turf underlayment pads; drainage improvements; lighting improvements; improvements and repairs to existing perimeter fence and gate systems; replace select site furnishings.
Funding Source
Funding comes from the Recreation and Parks Department General Fund and Playfields Fund.
Thank you for your patience while we complete these improvements.
Preparing to Bid Field Replacement Project
We are in the home stretch of preparing the bid package and plan to put this project out to bid by the end of January. Construction is anticipated to start in December 2019 and will run approximately 4 months.
Design Underway for Youngblood Coleman Turf Replacement
Verde Design, Inc. is moving along with the design of this project and we will be reviewing 90% construction documents shortly.