McLaren Park – Jerry Garcia Amphitheater Project

Jerry Garcia amphitheater from the ltop of the lawn area, showing the stage

Scope of Work

Includes extending flat paved space adjacent to accessible parking lot to allow for food trucks and other event services; delineating a route for temporary event fencing; and cosmetic upgrades and increased storage capacity in the greenroom

Funding

Funding comes from the 2012 Clean and Safe Neighborhood Park Bond in the amount of $1,450,000.

Timeline

Planning will resume in winter 2019, with project completion anticipated to occur in mid 2020.

Jerry Garcia Amphitheater Project Kickoff!

We are excited to be continuing the Jerry Garcia Amphitheater Improvement Project! The scope of the project is based on the extensive McLaren Park Vision Planning Process that has been in progress. We are planning on holding the 2nd Community Meeting in early May 2019. Stay tuned for more info.