Lake Merced Boat Dock Replacement Project

Existing Dock Photo Lake Merced Boat Dock

project Scope

Replace existing gangway and boat dock with new accessible facility that includes one parking, pathway, abutment, expanded gangway and boat dock.

Funding

$435,000             2012 Parks Bond- Community Opportunity Fund
$225,000             Grant-California Parks & Rec, Department of Boating/Waterways
$50,000             Board of Supervisors
$710,000             Total Fund Sources

Schedule

Planning:  March 2015
Design: March 2016
Bid/Award: TBD
Construction: TBD

Update:  The project is on hold until additional funding is identified. The project cost estimate is $1.8M. Both RPD and community have applied to grants to cover the shortfall.