Margaret Hayward Playground Renovation Update – Feb, 15 2019

Demolition is 85% complete – Only 1.5 buildings remain to be removed…and the first concrete footings will be poured next week.

Check out the formwork awaiting concrete trucks next week: Margaret S. Hayward Playground Renovation or cut and paste into your browser: https://sfrecpark.org/project/margaret-s-hayward-playground-improvement-project/

UPDATE ON TENNIS COURTS: Extending the tennis court closure through April 30, 2019.

Engineers and contractors are resolving the unforeseen structural condition on the south edge of the tennis courts. They will be replaced with new, continuous retaining wall and fencing. Unfortunately, the additional work will extend the closures through end of April for shoring, further demolition, concrete form work, concrete pour and fence installation.

We apologize for the inconvenience. Please visit nearby Tennis Courts at Hayes Valley, Hamilton and Alamo Square, see attached map.