Balboa Pool Construction Update!

The Balboa Pool renovation project has experienced delays related to the new electrical service connection to the facility. We are continuing to work with the contractor and utility providers including PG&E & PUC to complete construction as soon as possible. Installation of the new electrical service has begun, this week contractor is trenching and installing the new utility substructure through the site.

We are also making good progress on other aspects of the work on the interior and exterior to maintain progress. We greatly appreciate the community interest in the re-opening of the pool, and are excited to return the facility to the community.

We currently anticipate project completion in early 2019. We will make an announcement to our community email list and on this web page when we set the opening date.