Much progress has been made over the past couple months on the utilities, sitework and interiors. Highlights include formwork for the new North Stairs, Mechanical Enclosure steel columns, and Boiler System connections in the basement.
On the interiors, wall framing, drywall and insulation in locker room areas are near completion. The contractor is hard at work in the natatorium with pool gutter and tile install. Pool and mechanical/electrical/plumbing equipment and connections is on-going.
Completion and reopening of the pool is expected Spring of 2021.