News Flash

Bay View Playground Improvements (COF)

Posted on: September 20, 2021

Bay View Playground Renovation, update 9/2021!

Capital Project Update

The project is 85% completed! The sod was recently installed and needs 60 days for full establishment (recommended time for roots to attach to the earth and grow strong before being walked on) The fences are 90% installed, fixtures are starting to be installed, utilities are being tested, tweaked and retested before inspections in October.

A newly planted tree, new black chain link fences and new cement pathways. Square holes dug in the dirt next to the new black chain link fence and sodFitness equipment on top of round cement surrounded by new cement pathways, sod and treesNewly installed sod pieces

Additional Info...
Facebook Twitter Email