Angelo J. Rossi Pool Renovation

Posted on: March 9, 2021

Rossi Pool Project Update 3/9/21!

Capital Project Update

Project progress is moving along well, despite some recent construction delays due to unforeseen site conditions. Current construction activities include: Exterior window and doors installation, interior tiling, epoxy flooring, painting. Pool and mechanical work include waterproofing, trench drains, equipment connections, MEP Rough-ins and MEP Finishes.  Sitework/Utilities work includes placing manholes and catch basins. We are anticipating completion of construction in Early Summer 2021.

Interior restroom unfinished sink area with three mirrors and black doors in the stalls.

Interior room with white walls, floor covered in brown protective paper looking out at black shelves

Three construction wokers in orange safety gear working on the pool deck.

Interior of the building with four large windows, white walls and ceiling and black iron accents.

Exterior of the building with four large windows and construction workers on scaffolding.

Additional Info...
Facebook Twitter Email

Other News in Angelo J. Rossi Pool Renovation

Capital Project Update

Rossi Pool Project Update 7/19!

Posted on: July 19, 2021
Capital Project Update

Rossi Pool Project Update 4/28!

Posted on: April 28, 2021
Capital Project Update

Rossi Pool Project Update 10/28!

Posted on: October 29, 2020
Capital Project Update

ROSSI POOL PROJECT UPDATE

Posted on: June 27, 2018
Capital Project Update

ROSSI POOL RENOVATION PROJECT UPDATE

Posted on: January 6, 2020