Shoreview Park Renovation Project

Posted on: May 28, 2020

Shoreview Park Project Update 5/28!

Capital Project Update

The $1,784,000 contract awarded to JDB & Sons Construction for Shoreview Park Renovation Project started construction on November 18, 2019 and is currently 45% complete. The original substantial completion date of June 14, 2020 is extended to October 30, 2020 per construction change order for fabrication and installation of play structures and time extension per COVID-19 impact from directives of Order of Health Officer of the City and County of San Francisco.

Work completed includes demolition of concrete playground and paved areas, site survey and layout, excavation for ADA ramp and lawn area, grading and surplus soils off haul. Trenching for electrical conduits and irrigation lines is currently in progress. Concrete pathways, ADA ramp and foundations for light poles are scheduled in the month of June.  Progress construction photos are shown below. For playground features, see Site Plan and Play Structures drawings dated 10/16/19 that are included in Documents and Materials.  

Shoreview Park future ADA Ramp at the west entrance. Ramp is currently graded out with a soil substr

Shoreview Park future east entrance pathway shown here with dirt substrate, a mature tree on the lef

Shoreview Park future central plaza and playground area, seen here with dirt substrate material, mat

Shoreview Park circular dirt path by the unplanted lawn area. A black garbage can is on the right ha

Facebook Twitter Email

Other News in Shoreview Park Renovation Project

Capital Project Update

Shoreview Groundbreaking Event

Posted on: October 16, 2019
Capital Project Update

Shoreview Park Renovation Update

Posted on: August 14, 2019
Capital Project Update

Community Day

Posted on: June 15, 2019