News Flash

RPD Park Improvements | All Project Updates

Posted on: September 18, 2023

Buchanan Street Mall | Memory Walk design reviews + workforce development meetings this week!

Capital Project Update

Wrendering of Buchanan Street Mall Memory Walk by Public Works

This is a full week for the Buchanan Street Mall Renovations project!

The Buchanan Street Mall project team is seeking San Francisco Arts Commission Civic Design Review committee approval on the landscape features of the Memory Walk: decorative paving and gateway columns and tall fencing—with space reserved within these elements for interpretive and artistic content. An informational update will also be shared with the Recreation and Parks Commission. Please click here to view the Memory Walk Concept Design slides and see details below to participate in the meetings.

Trust for Public Land continues to lead design of the Memory Walk, in collaboration with Recreation and Parks, Citizen Film, and the African American Arts & Culture Complex. These four partners have framed programming that includes artist mentorship, community curation and participation, and a process for developing future art opportunities. These three Memory Walk program pieces will be further refined by partners and through additional community process this fall.

The project team continues to actively fund-raise for the Memory Walk program and future art opportunities, and future art opportunities will be presented to the Recreation and Parks Commission for approval in advance of releasing a public RFQ for original artwork. 

Civic Design Review – Monday 9/18 at 2pm

Hybrid: In-Person & via Webex

401 Van Ness, Ste. 125

San Francisco, CA 94102 


and

Rec and Park Commission (info update) – Thursday 9/21 at 10am

City Hall, Room 416

Remote comment is available for both Committee and full Commission meetings. Remote meeting instructions will be at the top of each meeting agenda with information about how to listen, view and comment at the meetings. 

In addition, the project’s Park Improvement Equity Action Initiative continues, as the Core Partners work to refine their recommendations.

Project Manager Lauren Dietrich Chavez continues to host office hours most Thursdays 2-3pm at the Opportunity Hub on Buchanan Mall, just south of Golden Gate Avenue. (Note there are no office hours Thursday 9/21). Stop by to discuss the draft recommendations or ask any questions you have about the capital project.

The Buchanan Mall project team has also committed to a monthly workforce development task force meeting, which will be hosted by Success Centers the third Wednesday of the month. Details below.

Workforce Development Task Force

Meetings every third Wednesday of the month

First meeting:

Wednesday, September 20th at 6pm

Success Centers Career Center, 1449 Webster Street

Additional Info...
Facebook Twitter Email

Other News in RPD Park Improvements | All Project Updates

Capital Project Update

Stow Lake Path Project Update - 2/13/2023

Posted on: February 13, 2023
Capital Project Update

Esprit Park Renovation Update 12/22!

Posted on: December 22, 2022
Capital Project Update

Herz Rec Project Update 12/20/22

Posted on: December 20, 2022
Capital Project Update

Twin Peaks Project Update 10/27/22!

Posted on: October 27, 2022
Capital Project Update

McLaren Park Vision Plan Update 10/26!

Posted on: October 26, 2022
Capital Project Update

Herz Recreation Center Update 10/26/22

Posted on: October 26, 2022
Capital Project Update

Herz Rec Construction Update 9/16!

Posted on: September 16, 2022
Capital Project Update

McLaren Park Vision Plan Update 9/16!

Posted on: September 16, 2022
Capital Project Update

Preparing for Tree Work at Esprit Park

Posted on: September 12, 2022
Capital Project Update

Great Highway Pilot Project Legislation

Posted on: September 2, 2022
Capital Project Update

Esprit Commission Presentation Sept 7!

Posted on: September 1, 2022
Capital Project Update

Herz Recreation Center Update 8/24!

Posted on: August 24, 2022
Capital Project Update

India Basin - Water Barrier Removed

Posted on: July 18, 2022
Capital Project Update

Art finalists for Herz Rec Center!

Posted on: July 6, 2022
Capital Project Update

Esprit Park Project Update 6/2!

Posted on: June 3, 2022
Capital Project Update

11th and Natoma New Park Survey!

Posted on: May 3, 2022
Capital Project Update

Twin Peaks Project Update 5/2/22!

Posted on: May 2, 2022
Capital Project Update

Esprit Park Project Update 4/28!

Posted on: April 28, 2022
Capital Project Update

Esprit Park Project Update 3/23/2022

Posted on: March 23, 2022
Capital Project Update

Esprit Park Project Update 2/23/2022

Posted on: February 24, 2022
Capital Project Update

Herz Playground Project Update 2/23/2022

Posted on: February 24, 2022
Capital Project Update

Gene Friend Rec Center Project Updates

Posted on: February 14, 2022
Capital Project Update

Public Art Opportunity at Ocean Beach!

Posted on: February 10, 2022
Capital Project Update

Rossi Pool Project Update 1/31/22

Posted on: January 31, 2022
Capital Project Update

Herz Playground Project Update 1/22!

Posted on: January 21, 2022
Capital Project Update

Herz Playground Project Update 12/17!

Posted on: December 17, 2021
Capital Project Update

Esprit Park Project Update 11/23!

Posted on: November 23, 2021
Capital Project Update

Herz Playground Project Update 11/18!

Posted on: November 18, 2021
Capital Project Update

Rossi Pool Project Update 11/2/21!

Posted on: November 2, 2021
Capital Project Update

Juri Commons is now open to the public!

Posted on: October 5, 2021
Capital Project Update

Esprit park Project News 9/30/21!

Posted on: September 30, 2021
Capital Project Update

Herz Playground Project Update 9/20!

Posted on: September 20, 2021
Capital Project Update

Herz Recreation Center Project Update 9/20!

Posted on: September 20, 2021
Capital Project Update

Esprit Park Project Update 9/11!

Posted on: September 10, 2021
Capital Project Update

Herz Playground Project Update 8/20!

Posted on: August 20, 2021
Capital Project Update

Rossi Pool Project Update 7/19!

Posted on: July 19, 2021
Capital Project Update

Herz Playground Project Update 7/19!

Posted on: July 19, 2021
Capital Project Update

Herz Playground Project Update 6/21!

Posted on: June 22, 2021
Capital Project Update

Esprit park Project News 6/14!

Posted on: June 14, 2021
Capital Project Update

Rossi Pool Project Update 4/28!

Posted on: April 28, 2021
Capital Project Update

Esprit park Project News 4/23/21!!

Posted on: April 23, 2021
Capital Project Update

Herz Playground Project Update 4/20!

Posted on: April 20, 2021
Capital Project Update

Esprit Park Renovation Update MAR '21

Posted on: March 29, 2021
Capital Project Update

Rossi Pool Project Update 3/9/21!

Posted on: March 9, 2021
Capital Project Update

Garfield Pool Project Update 3/9/21!

Posted on: March 9, 2021
Capital Project Update

News about the Herz Projects!

Posted on: February 23, 2021
Capital Project Update

Esprit park Project News 2/23!

Posted on: February 23, 2021
Capital Project Update

Juri Commons Construction Update 2/9!

Posted on: February 9, 2021
Capital Project Update

Richmond playground Project Update 2/9!

Posted on: February 9, 2021
Capital Project Update

Bayview Playground Project Update 1/29!

Posted on: January 29, 2021
Capital Project Update

Esprit park Project Update 1/22!

Posted on: January 22, 2021
Capital Project Update

Herz Playground Project Update 1/22!

Posted on: January 22, 2021
Document

GGP Dog Training Area December Update

Posted on: December 29, 2020
Capital Project Update

Golden Gate Heights Update Dec '20

Posted on: December 23, 2020
Capital Project Update

Esprit Park Renovation Update Dec '20

Posted on: December 23, 2020
Capital Project Update

Herz Playground Project Update Dec '20

Posted on: December 23, 2020
Capital Project Update

Francisco Park Construction Update DEC '20

Posted on: December 22, 2020
Capital Project Update

Margaret Hayward Project Update 11/18!

Posted on: November 19, 2020
Capital Project Update

Francisco Park Construction Update 11/12!

Posted on: November 12, 2020
Capital Project Update

George Christopher schedule update 11/5!

Posted on: November 6, 2020
Capital Project Update

Herz Playground Project Update 10/29!

Posted on: October 29, 2020
Capital Project Update

Rossi Pool Project Update 10/28!

Posted on: October 29, 2020
Capital Project Update

Esprit park Project Update 10/29!

Posted on: October 29, 2020
Capital Project Update

Garfield pool Renovation Update 10/27!

Posted on: October 27, 2020
Capital Project Update

Margaret Hayward Project Update 10/20!

Posted on: October 22, 2020
Capital Project Update

Gene Friend Rec Project Update 10/9!

Posted on: October 9, 2020
Capital Project Update

Geneva Powerhouse Project Update 10/9!

Posted on: October 9, 2020
Capital Project Update

Margaret Hayward Project Update 10/5!

Posted on: October 5, 2020
Capital Project Update

Middle Lake Design Pushing Forward 9/21!

Posted on: September 21, 2020
Capital Project Update

Juri Commons Construction continues 9/21!

Posted on: September 21, 2020
Capital Project Update

Herz Recreation Center Project Update 9/18!

Posted on: September 18, 2020
Capital Project Update

Esprit park Project Update 9/18!

Posted on: September 18, 2020
Capital Project Update

Herz Playground Project Update 9/18!

Posted on: September 18, 2020
Capital Project Update

Guy Place Project Update 8/21!

Posted on: August 21, 2020
Capital Project Update

Herz Rec Center Project Update 8/21!

Posted on: August 21, 2020
Capital Project Update

Herz Playground Project Update 8/21!

Posted on: August 21, 2020
Capital Project Update

Esprit Park Project Update 8/21!

Posted on: August 21, 2020
Capital Project Update

Jackson Playground Meeting Follow-Up

Posted on: August 6, 2020
Capital Project Update

Herz Rec Center Project Update 7/27!

Posted on: July 27, 2020
Capital Project Update

Esprit Park Project Update 7/24!

Posted on: July 24, 2020
Capital Project Update

Garfield Pool Project Update 7/22!

Posted on: July 23, 2020
Capital Project Update

Guy Place Project Update 5/22!

Posted on: May 22, 2020
Capital Project Update

Esprit Park Project Update 5/22

Posted on: May 22, 2020
Capital Project Update

Garfield Pool Project Update 5/13!

Posted on: May 13, 2020
Capital Project Update

Guy Place Project Update 5/1!

Posted on: May 1, 2020
Capital Project Update

Esprit Park Project Update 4/17

Posted on: April 17, 2020
Capital Project Update

Herz Playground Project Update 4/17

Posted on: April 17, 2020
Capital Project Update

Lake Merced Project Update 3/31!

Posted on: March 31, 2020
Capital Project Update

Esprit Park Project Update

Posted on: March 23, 2020
Capital Project Update

Guy Place Construction Update

Posted on: March 23, 2020
Capital Project Update

McLaren Park 3/7 Trails Walk Recap

Posted on: March 11, 2020
Capital Project Update

SGT MACAULAY PARK NEARING COMPLETION

Posted on: March 5, 2020
Capital Project Update

TURK-HYDE MINI PARK REOPENS!

Posted on: March 2, 2020
Capital Project Update

GUY PLACE PROJECT UPDATE FEB 21 2020

Posted on: February 21, 2020
Capital Project Update

GUY PLACE ROAD CLOSURE FEB 19 2020

Posted on: February 19, 2020
Capital Project Update

CONSTRUCTION UPDATE FEB 2020

Posted on: February 11, 2020
Capital Project Update

WASHINGTON SQUARE UPDATE- FEB 2020

Posted on: February 7, 2020
Capital Project Update

GUY PLACE CONSTRUCTION UPDATE FEB 2020

Posted on: February 6, 2020
Capital Project Update

NEXT TRAIL WALK SCHEDULED FOR MARCH 7

Posted on: February 5, 2020
Capital Project Update

CONSTRUCTION UPDATE- FEB 2020

Posted on: February 3, 2020
Capital Project Update

ESPRIT PARK WORKSHOP- CONCEPT PLAN

Posted on: January 31, 2020
Capital Project Update

Juri Commons Renovation Moving Forward!

Posted on: January 29, 2020
Capital Project Update

ROSSI POOL RENOVATION PROJECT UPDATE

Posted on: January 6, 2020
Capital Project Update

Bernal Heights - CONSTRUCTION ONGOING

Posted on: January 6, 2020
Capital Project Update

GENE FRIEND REC CENTER PROJECT UPDATES

Posted on: January 4, 2020
Capital Project Update

Fillmore Turk Mini Park Community Meeting

Posted on: December 31, 2019
Capital Project Update

HERZ PLAYGROUND

Posted on: December 18, 2019
Capital Project Update

ESPRIT PARK COMMUNITY OUTREACH UPDATE

Posted on: December 18, 2019
Capital Project Update

WASHINGTON SQUARE REOPENS- DEC 2019

Posted on: December 11, 2019
Capital Project Update

Richmond Playground Open House- Thank You!

Posted on: December 11, 2019
Capital Project Update

TURK-HYDE CONSTRUCTION UPDATE

Posted on: December 4, 2019
Capital Project Update

HERZ- CHILDREN’S PLAYGROUND RENOVATION

Posted on: November 20, 2019
Capital Project Update

POP-UP PLAYDATE AT ESPRIT PARK!

Posted on: November 18, 2019
Capital Project Update

GUY PLACE STREET UTILITIES

Posted on: November 15, 2019
Capital Project Update

ESPRIT PARK RENOVATION

Posted on: November 6, 2019
Capital Project Update

Richmond Playground Open House

Posted on: November 2, 2019
Capital Project Update

TURK-HYDE CONSTRUCTION UPDATE

Posted on: October 18, 2019
Capital Project Update

Shoreview Groundbreaking Event

Posted on: October 16, 2019
Capital Project Update

FILLMORE TURK MINI PARK – OCTOBER 2019

Posted on: October 11, 2019
Capital Project Update

FILLMORE TURK MINI PARK – OCTOBER 2019

Posted on: October 11, 2019
Capital Project Update

BUENA VISTA PARK – COMMUNITY MEETING

Posted on: September 27, 2019
Capital Project Update

GGP DOG TRAINING AREA PROJECT UPDATE

Posted on: September 20, 2019
Capital Project Update

HERZ REC CENTER PLANNING PHASE UPDATE

Posted on: September 20, 2019
Capital Project Update

BERNAL HEIGHTS CONSTRUCTION UPDATE

Posted on: August 20, 2019
Capital Project Update

Shoreview Park Renovation Update

Posted on: August 14, 2019
Capital Project Update

GENEVA CAR BARN CONSTRUCTION UPDATE

Posted on: July 11, 2019
Capital Project Update

India Basin - Design Survey

Posted on: June 21, 2019
Capital Project Update

WASHINGTON SQUARE CLOSURE- JUN 2019

Posted on: June 17, 2019
Capital Project Update

Shoreview Park - Community Day

Posted on: June 15, 2019
Capital Project Update

Let’sPlaySF! Groundbreaking

Posted on: April 12, 2019
Capital Project Update

GARFIELD POOL – CONSTRUCTION UPDATE

Posted on: March 27, 2019
Capital Project Update

FRANKLIN SQUARE CONSTRUCTION UPDATE

Posted on: March 8, 2019
Capital Project Update

REDWOODS IN JURI COMMONS??

Posted on: February 13, 2019
Capital Project Update

TWIN PEAKS FIGURE 8 REDESIGN NEXT STEPS

Posted on: February 4, 2019
Capital Project Update

OAK WOODLANDS PROJECT UPDATE- JAN 2019

Posted on: January 19, 2019
Capital Project Update

GENEVA CAR BARN CONSTRUCTION

Posted on: October 17, 2018
Capital Project Update

DESIGNER SELECTED FOR BUCHANAN MALL

Posted on: September 7, 2018
Capital Project Update

JURI COMMONS DESIGN APPROVED

Posted on: September 7, 2018
Capital Project Update

FRANCISCO PARK UPDATE

Posted on: September 7, 2018
Capital Project Update

GENEVA CAR BARN CONSTRUCTION UPDATE

Posted on: August 23, 2018
Capital Project Update

ROSSI POOL PROJECT UPDATE

Posted on: June 27, 2018
Capital Project Update

BUCHANAN STREET MALL PROJECT UPDATE

Posted on: June 21, 2018
Capital Project Update

FRANCISCO PARK PROJECT UPDATE

Posted on: May 16, 2018
Capital Project Update

TWIN PEAKS FIGURE 8 REDESIGN UPDATES

Posted on: February 21, 2018
Capital Project Update

FRANKLIN SQUARE-DEC 2017 UPDATE

Posted on: December 26, 2017