Hi all- We are pleased to report that on August 18, the RPD Commission approved the contract award for the construction of Stow Lake. Pre-construction coordination will begin at the end of September with an anticipated construction start date of early October. In total, the estimated length of construction is 9 months, concluding in late spring, 2023. The work is split in two phases so that one half of the perimeter pathway remains open at any given time. Special attention will be paid to wildlife, as a biologist will monitor activities over the course of the project. Construction administration and management will be supported by SF Public Works.
Stow Lake Boathouse, restrooms, parking, and Stow Lake Drive will remain open throughout the duration of the project.
For questions, please reach out to Project Manager, Omar Davis, at omar.davis@sfgov.org.