Notice to Proceed for pre-construction services was awarded to Swinerton Builders just prior to Thanksgiving, and they have hit the ground running, working with the design team to review documents and start cost estimating and constructability. As a reminder, this project is using the CM/GC contract mechanism, where the contractor team, and core trade subcontractors, embark on several rounds of cost estimating and constructability review and reconciliation with the architects and project team.
Phase 2 environmental testing was also completed this month, as part of compliance with the Maher Ordinance.
The project team is expecting to have lots more updates for the community within the first month or two of 2023, including design and schedule updates. Rec and Park will also be teaming up with the Arts Commission to convene a meeting to review the process for incorporating arts enrichment into the project.
Happy Holidays and stay tuned for more detailed updates in January!