South Sunset Clubhouse

Background

South Sunset Playground is a 4-acSouth Sunset Clubhouse rendering credit Paulett Taggart Architectsre park featuring ball fields, basketball and tennis courts, a playground, a paved multi-use play area and the clubhouse. The 2,000 square-foot single-story clubhouse includes a multi-purpose room, restrooms, a kitchen, and an office. The building was originally constructed in 1949, renovated in 2001, and is in need of repair to better serve the community.  The current tenant is Self-Help for the Elderly, and they currently provide hot meals and programming to over 200 seniors. The park site was included in the 2020 Health and Recovery G.O. Bond with the support of the District Supervisor.  


Scope of Work

Planned improvements to the park include the reconfiguration and renovation of interior spaces in the clubhouse, access improvements, and beautification. 

Funding

  • 2020 Health and Recovery G.O. Bond 
  • FY 22-23 State Budget Specified Grant.

Project Schedule

PhaseTimeline
PlanningFall 2022
DesignSummer 2023
ConstructionLate 2024
Open to the publicLate 2025


Project Updates

If you would like to sign-up for Project Update blog posts like the ones below, click here, scroll down to the News Flash section, and then select "RPD Park Improvements | All Project Updates" to receive updates on all our active projects, or pick-and-choose your blog subscriptions by project name. You’ll receive an email that includes a link to confirm your new subscription for each blog for which you sign-up.

  1. Project Update Blog
  2. Documents and Materials
  1. Capital Project Update

    South Sunset Clubhouse Renovation | REMINDER: Project Open House this Friday, Nov 3, 10 to 11:30 am

    Reminder that our Open House is this Friday, November 3, 2023, 10 to 11:30 a.m., at the South Sunset Clubhouse (2601 40th Avenue. San Francisco, CA 94116). Read on...
  2. Capital Project Update

    South Sunset Clubhouse Renovation | Project Open House on Friday, November 3, 10 to 11:30 am

    Join us for an Open House at South Sunset Clubhouse on Friday, November 3, 10 to 11:30 a.m., to discuss plans to renovate the clubhouse Read on...
  3. Capital Project Update

    South Sunset Clubhouse | Project Update October 2023

    South Sunset Clubhouse will be renovated beginning in late 2024 with a projected opening slated for the end of 2025. As we announced in our Read on...
  4. Capital Project Update

    South Sunset Clubhouse | Project Update August 2023

    We have brought Paulett Taggart Architects onboard as our project designers for South Sunset Clubhouse to work alongside the mechanical and structural engineers from San Francisco Public Works. Currently, the architects are developing Read on...
  5. Capital Project Update

    South Sunset Clubhouse | Project Update June 2023

    Rec and Park has completed our review of proposals for the complete renovation of the interior spaces of South Sunset Clubhouse Read on...
  6. Capital Project Update

    South Sunset Clubhouse | Project Update May 2023

    We are currently reviewing proposals for a complete renovation of the interior spaces that were Read on...
  7. Capital Project Update

    South Sunset Clubhouse Project Update 1/23!

    The Public Works design team is developing a concept plan for the renovations at the Clubhouse that . . . Read on...
  1. Eoanna Harrison Goodwin

    Project Manager