South Park update 01/27/17

The grades under the playground structure were shaped and compacted to prepare for the safety surface installation that will take a few weeks. Once it is completed, the entire playground structure, connectors, openings, will be inspected to confirm they comply with safety standards. This structure is accessible from multiple areas allowing for play above and below.

Expect the following in the coming weeks:

  • Week 01/30/2017.
    • playground installation, continued
    • safety surface installation (2 weeks)
    • sod establishment
    • site furnishings installation, continued (trash cans/lights)
  • Week 02/6/2017
    • playground installation, continued
    • safety surface installation
    • testing/inspection
    • sod establishment
    • site furnishings installation, (plaques/lights)
  • Week 02/13/2017 
    • playground installation,
    • testing/inspections
    • sod establishment/plant install
    • site furnishings installation TBD, (signage)