South Park Renovation Update 1/20/17

 

SouthParkPlayground

Photo credit: Fletcher Studios

Wow! The playground structure looks complete, but …..this incredible state of the art playground is carefully inspected to make sure each connection and opening comply to safety standards. The testing and inspection started last week and adjustments will continue into next week when the weather clears up. Once approved the safety surface underlayment — which take several weeks — will be installed.

A brief schedule for the next few weeks are:

Week 01/23/2017

  • playground installation and inspections, continued
  • netting adjustments
  • fine grading/mound formations, continued
  • sod establishment
  • site furnishings installation, benches

Weeks 01/30/2017 and 02/6/2017

  • playground installation, continued
  • safety surface installation
  • sod establishment
  • site furnishings installation, continued

Week 02/14/2017

  • playground installation, continued
  • testing/inspections
  • sod establishment
  • plant install,
  • site furnishings installation, final adjustments

Site furnishings consist of signage, benches, tables, trash receptacles, fixtures, lights,  plaques, etc.