SF Lawn Bowling Green 1-update 09/2014

The project is 85% complete!

View from northwest corner

View from northwest corner

Concrete sidewalks are completed and the metal fence was installed last week. The crows enjoy digging for worms in the new sod which is causing a daily ruckus.

In the next four weeks, the gate hardware,  guardrails and accessible bridge over the gutter will be installed. Stay tuned.

Clubhouse entrance to green

Clubhouse entrance to green

Northeast access to green

Northeast access to green