Street Soccer Coming to The City in June

The City has announced plans to host the Street Soccer USA West Coast Cup, a tournament to raise awareness for homelessness and bridge the gap between our various communities, in June.  The tournament will include homeless teams from cities across the nation, playing and competing with corporate teams. The San … Continue reading

Important information about all RPD pool schedules the week of May 28th to May 31st.

90 % of our staff will be in re-certification training during the week of May 28th to 31st. Our pools will be on a limited schedule that will vary greatly from both the spring and summer schedules. We will have the pools open with a limited staff. This will mean limited hours, … Continue reading

Update on Construction: Making Steady Progress

Hi Folks – Overall, the project is now about 30% complete.  Recently, the construction crew has been busy working on the new retaining walls for the tennis courts.  Soon, you can expect to see more grading as we start to construct the new tennis courts. The contractor has also been hard at work inside … Continue reading

City Scores Victory for Kids, Soccer

Great news! The California Coastal Commission voted unanimously today to uphold the permit for the Beach Chalet Athletic Field renovation project at the West End of Golden Gate Park, perhaps the most vetted public project in Rec and Park history. The Commission’s vote means the renovation project can move forward … Continue reading

Give Make & Go

Join us for free arts and craft activities and live music! We will be hosting a Art & Music Donation Drive!  Requested donations: Art supplies, craft supplies, fabric, framed artwork, frames, sewing/knitting supplies, sculptures, musical instruments, sheet music, tapes, records, CDs, electronic instruments, stereos, record players, recording devices, and other audio … Continue reading

Art in the Park

Have you checked out San Francisco Recreation and Parks summer day camp offerings?  Art In The Park is a non-​​competitive camp for cre­ative expres­sion. Stu­dents attend three art classes each morn­ing. On Fri­day, campers visit local Golden Gate Park muse­ums and attrac­tions to prac­tice draw­ing tech­niques. There is an Art Show … Continue reading

Mandatory staff recertification training– all pools closed- May 28 to May 31 from 8AM until 12:30 PM

From Tuesday, May 28 to Friday May 31st, 2013, all RPD swimming pools will be closed for mandatory staff re-certification training. During this week we will have limited pool hours with minimal staffing during the early mornings and afternoons/evenings. These limited schedules will be posted May 10, 2013, as we are currently working to … Continue reading

Mission Pool Improvements_2nd Phase commences

The Pool locker room work (first phase) is substantially complete. (see attached pics) The second and final  Phase of the Pool Improvements have commenced. Demolition of the existing concrete slab is complete. Contractor is now trenching for new slot drains and new main drains. A brand new pool recirculation piping and pump … Continue reading

Balboa Pool Heat/Exchange was down, but has been repaired

This morning, our stationary engineers discovered that the heat/exchange unit at Balboa Pool was down. After working on it during the morning, they recently finished its repair, but the pool is currently 76 degrees. We expect the pool temperature to rise over the next twenty four hours, but as of this moment it is … Continue reading

Martin Luther King Jr. children’s pool closed until further notice

On Sunday, April 7 the stationary engineers discovered that the feeding system for the children’s pool, the small pool, was not working. This is resulted in chlorine levels dropping below state-mandated levels. Therefore the pool is closed until we’re able to resolve this issue. We apologize for the inconvenience.

Coffman pool boiler heating unit down, pool is not heated – Updated April 12, 2013

On Sunday, April 7 the stationary engineers discovered an internal leak in the boiler unit at Coffman pool. The unit had to be shut down, while the engineers discover the source of the leak, order parts, and repair the unit. During this time, the pool cannot be heated. Currently, the … Continue reading

Car-Free Saturdays Begin April 6

Car-free Saturdays along portions of JFK Drive in Golden Gate Park begin Saturday, April 6, 2013. Every Saturday through September, JFK Drive, from Tea Garden Drive (near 8th Avenue) to Transverse Drive, will be closed to vehicular traffic, allowing for bicyclists, walkers, joggers, skaters and others to enjoy a wide … Continue reading

Aquatics meeting and training days shifting from Tuesdays to Thursdays

Over the past year, the aquatics division reorganized itself in an effort to maximize our efficiency and provide more hours of operation. Over that time we increased our total hours, and went from having one swimming pool open on Sundays to having five swimming pools open. This entailed changing staff … Continue reading

City Invitational a huge success

   The San Francisco Recreation & Park Department with its partners, MLK Blue Dolphins and STARS (San Francisco Boys and Girls Club) hosted the City Invitational age group swim meet at Martin Luther King Jr. swimming pool. Over two days, 300 participants with their families, enjoyed a fantastically successful swim … Continue reading

Senior Get-a-way to Camp Mather 2013

Senior Get-a-way to Camp Mather 2013 55 and better! Camp Dates: August 18-22, 2013 (Sunday-Thursday) In Person Lottery Sign Up Registration Dates: 4/22,4/23,4/24,4/25,4/26,4/27,4/29,4/30,5/1,5/2,5/3 from 10:00 AM-1:00 PM in the front office of The Golden Gate Park Senior Center (6101 Fulton Avenue, SF CA 94121) Price: Residents: $273 Non-Residents: $306 Please, call Katherine … Continue reading

Mission Pool Improvements_ Progress continues

The first phase of the work (Pool Locker Room Improvements) is approximately 75% complete and it is expected to be complete by Mid  March so that the Pool Deck and systems can commence right away.Tile work is ongoing, fixture installation will commence next, interior to follow afterwards. Exterior stucco work will … Continue reading

M.L. King Jr. Swimming Pool is hosting City Invitational Age Group Swim Meet March 2 & 3 2013

San Francisco Recreation and Park Department, M.L.K. Blue Dolphins, and San Francisco Boys and Girls Club are co-hosting the City Invitational age group swim meet at Martin Luther King Jr. Swimming Pool on March 2 & 3, 2013. The pool will be closed to the public for swimming on those … Continue reading

Palega Construction_Progress Continues Feb 2013

Project is 65% complete. Contractor continues to make progress on duct work, wall framing, exterior sheating and wall insulation. Steel window repairs are also ongoing. Plaster repairs are also underway on the exterior. The strutural steel work is proceeding on the addition, contractor is also prepping tp pour structural slab … Continue reading

All RPD Pools closed Monday February 18, 2013 in observance of President’s Day

All of our aquatic facilities will be close on Monday February 18, 2013 in observance of President’s Day. We will reopen for our usual programming on Tuesday February, 2013.

Teen Musical Theatre Production of “Godspell”

This February, come see Rec and Park’s Young People’s Teen Musical Theatre Company’s production of “Godspell“, the gospel of St. Matthew told through hippie characters living in New York City in the late-1960s and early-1970s.  TICKETS: $15 general; $10 student/seniors can be purchased brownpapertickets.com. For more information, click here, or … Continue reading

Glen Canyon Park Renovation Project Underway!

Hi folks, As you might have noticed, starting last week, the renovation project is underway!  The project is anticapated to be completed in November of 2013, assuming no additional delays. As a reminder, major improvements include: a new children’s play area that will be almost twice as large as the … Continue reading

All pools closed in observance of ML King Jr. day on January 21st

All of our aquatic facilities will be close on Monday January 21, 2013 in observance of Dr. Martin Luther King Jr. We will reopen for our usual programming on Tuesday January 22, 2013.

FYI – Other work in park, trail improvements north of Rec Center, along “Saddle Area”

Hi folks, Just in case you notice and were wondering, there will be some work on one area of the trails in Glen Canyon Park, north of the rec center, called the “saddle area”  It is north of the boardwalk and near the climbing rocks.  It will see improvements beginning January 15, … Continue reading

Construction to Start on Glen Canyon Park Renovation Project – Portions of the Park Around Elk Street Closed Stating January 10th, other portions closed starting the week of January 14th

Hi Everyone – The contractor hired to start the Glen Canyon Project will be starting construction activities Thursday, January 10th.  At times, on  Thursday January 10th and January 11th, and the week of  January 14th tennis courts may be closed in order to protect park users during some work. It … Continue reading

Palega construction continues_ Jan 2013

After a very wet winter December, construction crews are mobilized fully for the week starting Jan 7th 2013. Project is 55% complete. Seismic work in the Gym continues, roofing at the upper level is substantially complete. Hydronic heating installation have commenced, rough electric and plumbing is ongoing, Fire sprinkler installation … Continue reading

Garfield Pool reopening delayed until January 11

“We are sorry to inform everyone that Garfield Pool will not open on Tuesday, January 8th. We hope to have the pool open for Friday, January 11th early morning swim. Currently 4 of the 5 items outlined in the inspector’s report have been addressed and corrected. A part for pool installation is … Continue reading

Garfield Pool reopening delayed…status will be updated on Monday evening 01-07-13

Garfield pool will not be opening on January 6, 2013 as scheduled. Upon review of the completed work, the inspector did not feel that the progress was adequate to allow for the pool to be opened on Sunday. We are contacting people who are registered for swim lessons to inform … Continue reading

Update on Glen Canyon Project, CEQA Appeal Found Untimely and Upcoming Project Update Meeting, January 7th

GlenPark Renovation Project – Project Update Meeting 1 7 13 Greetings and happy holidays from the Recreation and Park Department! We are looking forward to starting park renovation project at Glen Canyon Park. As you may have heard, the schedule has been delayed from the original start date of October … Continue reading

Glen Canyon Renovation Project Update – Rehearing Request on Building Permit Appeal Withdrawn and CEQA appeal filed

Hi Everyone, Another update - the appellant withdrew their re-hearing request today, so there is no hearing tonight, I am very sorry if you got this news too late, and already left for City Hall.  I heard late in the day myself.  The appeals board ’s vote of 4-0 to deny the appeal, is now … Continue reading

Mission Pool is Opening in Summer 2013

We apologize for the current delay related to unforeseen conditions discovered during the pool renovation.  The deterioration of the pool, building and the foundation systems were discovered to be in a more severe condition during the project.  Additional replacements of locker room walls, pool deck, drain system, pool plumbing, and filtration … Continue reading

Update on Building Permit Rehearing Request on Glen Park Renovation – Scheduled for December 12th

Hi Everyone, Here is the latest update: As you know, the appeals board voted 4-0 to deny the appeal on November 14th. The appellant had a 10 day period to file a re-hearing request. The last to file this request was November 26th. On that date, the appellant submitted a … Continue reading

Update – Glen Canyon Project, Building Permit Appeal, Re-Hearing Request Filed

Hi Everyone, Quick update about the appeals process. As you know, the appeals board voted 4-0 to deny the appeal, but the appellant had a 10 day period to file a re-hearing request. The last to file this request was November 26th. On that date, the appealant submitted a re-hearing … Continue reading

See us change

Hi! For those of you who have visited the Aquatics page before, you might have noticed something different. It looks different. Over the coming months, we are making changes to this page to give you better and more timely information. To help you along, if you are looking for pool schedules, just … Continue reading

Garfield Pool closed until January 6, 2013 for restroom improvements

Currently we are working with Mayor’s Office on Disability to conduct much needed restroom access improvements. This has necessitated a longer closure period that the typical annual pool closure for general maintenance. The pool closed on November 17, 2012. The pool is projected to reopen on January 6, 2013. During this closure, we have moved … Continue reading

Project Delayed – Appeal Filed on Building Permit – Update Soon!

Hello Everyone – As we have planned and communicated in flyers and elsewhere, we were planning on starting construction in mid October, this week on this project. However, on Monday an appeal was filed on the building permit that had been issued for the project. The permit and the project … Continue reading

Scaregrove!

Come to Scaregrove! Saturday, October 27, 3:00 p.m. to 9:00 p.m. Stern Grove, 19th Avenue and Sloat Accessible Van Shuttle! Accessible hay rides! Visit SFRecPark.org for more info Accessible parking on Sloat Blvd. between 21st and 23rd Avenues. For more info on accessibility, please contact our Inclusion Coordinator, Vicky Pitner, … Continue reading

Glen Canyon Park Renovation Update and Additional Information on Tree Work and Recent Tree Failures

Hi everyone, As you may know, the Glen Canyon Park Renovation Project will begin soon! As a reminder, major improvements include: a new larger children’s play area, new tennis courts, improved park paths, an improved Elk Street entry, a new accessible restroom, new landscaping, and new heating in the Recreation … Continue reading

Update on Glen Canyon Park Renovation, Notices of Tree Removals and New Tree Planting Information

As part of the upcoming Park Renovation Project, today a number of trees around the lower portion of Glen Canyon Park were posted with notices that the tree will be removed as part of the renovation. As a reminder, this project, which came out of a two year community planning … Continue reading

SF Chronicle: Betty Ann Ong Chinese Rec Center Reopens

The Chinese Recreation Center, known for years as Chinatown’s unofficial backyard, will reopen Saturday with a new name and a sparkling $21 million building, but the same commitment to providing a spot for sport, play and relaxation in one of the nation’s most densely populated communities. The center “is at … Continue reading

BETTY ANN ONG CHINESE RECREATION CENTER OPENS IN CHINATOWN

Connie Chan, SF Rec and Park 415-895-0689, connie.chan@sfgov.org BETTY ANN ONG CHINESE RECREATION CENTER OPENS IN CHINATOWN Investment in Recreation & Parks for San Francisco Families, Newest $21 Million Capital Improvement Project from the 2008 Parks Bond Completed San Francisco, CA—TodayMayor Edwin M. Lee joined Board of Supervisors President David … Continue reading

Glen Canyon Park/Playground Improvements – Getting Contractor On Board

Apologies for our blog-writing hiatus! We’ve been busy finishing the design drawings for what is certain to be a fantastic renovation of Glen Canyon Park. Right now, we are completing the bid of the construction contract to a qualified construction company. We are on schedule to start construction on October. … Continue reading

Thank you for your continued interest and participation in the renovations at Glen Canyon Park

Thank you for your continued interest and participation in the renovations at Glen Canyon Park—from attending community meetings to emailing your thoughtful comments. The completion of a series of productive and informative community meetings marks the end of the planning stage of the Glen Canyon Park Renovation project. The project … Continue reading