Update and Notice: Glen Canyon Park Tennis Court Repair Work to Start September 2nd, Please Plan Accordingly

Hi Everyone, As you may have heard, it has come to our attention that the slope of the tennis courts at Glen Canyon Park are not in line with current United States Tennis Association (USTA) recommendations. Rec and Parks has worked with the design and construction management staff at the … Continue reading

Update on Public Art Process for Glen Canyon Park Rec Center Project

Hi Folks, Just want to update you about the Artist Selection Panel meeting on August 4th. Thank you again for all of your feedback. On August 4th, 2014 the finalists for the Glen Canyon Park Public Art Project presented their artwork proposals to the Artist Selection Panel. After careful review … Continue reading

Glen Canyon Project Updates: Rec Center Design Development, Art Commission Hearing and more

Hi folks, Last night I made a presentation to the Glen Park Neighbors Meeting at the Rec Center, where I showed a powerpoint. see below. Rec Center Renovation Design Development Please see the presentation to see developments in the design. Due to project costs, escalation, additional work needed to renovate … Continue reading

Glen Canyon Improvement Project Updates from Rec and Park: Update Tomorrow, July 30th at Glen Park Neighbors Meeting at Glen Canyon Rec Center

Hi Folks, Just an FYI  – I will be providing a project update at the Glen Park Association Quarterly Meeting at the Glen Park Rec Center tomorrow evening, July 30th.  The meeting officially starts at 7:00pm, but people can arrive at 6:30pm. Topic to cover include: Updates on the ongoing … Continue reading

Volunteers needed at Glen Park – Hillside Weeding – 9am to Noon, This Friday, June 27th!

Thank you again to those of you that came out and volunteered on the hillside Friday, June 13th!  It was great! That combined with the work of our gardening staff over the last few week, we have been focusing on taking out the radish and the mustard, starting at the … Continue reading

Comment Period Extended: Glen Canyon Recreation Center Renovation Proposals for Public Art Feedback accepted, Through July 8th

Hi Everyone! As some of you may know, all public capital projects like the upcoming renovation of the Glen Canyon Recreation center, include a public art component. We have been working with the San Francisco Arts Commission and the Department of Public Works artists to develop artwork that will highlight … Continue reading

Upcoming Glen Canyon Rec Center Renovation Proposals for Public Art needs your Feedback.

Hi Everyone! As some of you may know, all public capital projects like the upcoming renovation of the Glen Canyon Recreation center, include a public art component. We have been working with the San Francisco Arts Commission and the Department of Public Works artists to develop artwork that will highlight … Continue reading

Glen Canyon Tennis Courts Update

Hi Everyone, I wanted to provide an update on the tennis courts at Glen Canyon. It has come to our attention that the slope of the courts are not in line with current USTA recommendations. Rec and Parks has worked with the design and construction management staff at the Department … Continue reading

Glen Canyon Park Trail Naming Contest

Part of the plan for improving trails at Glen Canyon Park is installing some new signs to help park users find their way around and interpret the unique ecological features of the Canyon. We are running a trail naming contest to name these trails.  Please click on the link below … Continue reading

Glen Canyon Park Playground Reopens March 15

Join Supervisor Scott Wiener, SF Rec and Park GM Phil Ginsburg, the Glen Park Association and park advocates for the opening celebration of the newly renovated Glen Canyon Park Playground, Saturday, March 15, at 9:30 a.m.  For decades, locals have enjoyed the beautiful natural landscape and varied recreational offerings at … Continue reading

Playground Opening – March 15th! Come!

You are cordially invited to join Supervisor Scott Wiener, San Francisco Recreation and Park Department General Manager Phil Ginsburg, Glen Park Association and park advocates for the opening celebration of the Glen Canyon Park Playground.   Saturday, March 15th, 2014 9:30 a.m. Welcome Remarks and Ribbon Cutting Ceremony SF Rec … Continue reading

Update on Glen Canyon Playground Project Renovation: Nearing Completion and the Rec Center is Open Again

2008 Bond Project: As of January 7th, the Recreation Center is open!  The Rec Center is open with a new heating system and ready to be enjoyed on the following dates and times: Tuesday – Friday:             9 am – 9 pm Saturday:                            9 am – 5 pm Please note that … Continue reading

Update on Glen Canyon Playground and Tennis Court Project: Project Nearing Completion…

Hi Folks, Just wanted to provide an update – as you can see if you have been near the project soon,  The Glen Canyon Playground and Tennis Court Project is really moving along, if you see the park now, you will see that the new tennis courts are in place, … Continue reading

Update on Glen Park Rec Center Renovation Project in design – On to Civic Design Review Monday!

Hi Everyone – Just wanted to update you – for those of you are that are still interested to see EVEN more of us, as I mentioned in my last email update and blog post, the design team will be presenting the current design (first of 3 times) to the … Continue reading

Update, Next Steps on the Glen Canyon Rec Center Project: Rec Park Commission Review and Continued Work on Design

Hi Everyone – Thanks so much to those of you who were able to attend or otherwise provide feedback on the materials presented at the community meetings we held on the Renovation of Glen Canyon Park Recreation Center on June 13th and July 13th and the Open House/Update Meeting on November … Continue reading

Update on Glen Canyon playground renovation!

Hi Folks, I know many of you are eager for an update. The Glen Canyon Playground and Tennis Court Project is really moving along, if you see the park now, you will see that the new tennis courts are in place, and the new playgrounds are emerging. Over the next … Continue reading

Glen Canyon Recreation Center Renovation Design Update /Open House at Glen Park Library, November 20th

Hi Everyone – Thanks so much to those of you who were able to attend the community meetings we held to discuss the renovation of the Glen Canyon Park recreation center on June 13th and July 13th of this year.  The information and feedback from those meetings is available on the Glen Canyon … Continue reading

Glen Canyon Playground Renovation Update: and Work Planned Elk Street Sidewalk Starting Soon and Monday Oct 28th at Bosworth Entrance

Hi Folks, The Glen Canyon Playground and Tennis Court Project is moving along, if you see the park now, you will see that the tennis courts and playground are emerging.  In addition, we are finishing the limited work at the Bosworth Entrance (to replace the swing gate, etc.) and along … Continue reading

Glen Canyon Project Update: Work on the 14th on the Bosworth Entrance Area and Connection to Alms Road, Limited Access

Hi Folks, As I noted in my last blog post and eblast, you are now seeing some limited work done a bit north of the fenced off area, around the Bosworth Entrance (to replace the swing gate, etc.) and along a portion of the connection to the road north of … Continue reading

Update on Glen Canyon Park Playground/Tennis Court Renovation

Hi folks, I wanted to provide you all an update on the project’s progress.  Things are going relatively well, and the work is well underway.  As you might notice, the contractor has been installing form work and rebar for the new playground area and the tennis courts and is starting … Continue reading

Glen Canyon Park Playground Project: Update on Construction – Still moving along…

Hi folks, We continue to make progress on construction.  As you might notice, the contractor has started to install form work and rebar and layout the various walls for portions of the tennis courts and playground areas. As often happens, we did encounter some complications, as we founds some of … Continue reading

Glen Canyon Rec Center Renovation – Great meeting last week – Meeting Info and Materials Now Online

Hi Everyone! As many of you may know, thanks to the community planning process in 2010-2011 which identified the needs for renovation and improvement of the facilities at Glen Canyon Park, not only is the playground and tennis court renovation in construction now, the Recreation Center Building Renovation was funded … Continue reading

Reminder: Upcoming Glen Canyon Park Recreation Center Renovation Community Meeting Saturday, July 13th at the Glen Canyon Rec Center, 10:30 am – 12:30 pm

Hi Everyone! Thanks to all of you that attended the community meeting in June and provided your feedback on the Rec Center Renovation Plan.  The next meeting is Saturday, July 13th.  I hope you can make it! Please see below and the meeting flyer for additional info – again, please feel … Continue reading

Glen Canyon Rec Center Renovation – Great meeting last week – Meeting Materials Now Online

Hi Everyone! As many of you may know, thanks to the community planning process in 2010-2011 which identified the needs for renovation and improvement of the facilities at Glen Canyon Park, not only is the playground and tennis court renovation in construction now, the Recreation Center Building Renovation was funded … Continue reading

Reminder: Glen Canyon Recreation Center Renovation Meeting THIS Thursday, 6/13/13 – at St. John School

Greetings! I just wanted to send everyone a quick reminder that we are holding a community meeting regarding the renovation of the Glen Canyon Park Recreation Center THIS Thursday, June 13th, at St. John School, located at 925 Chenery Street.  Additional details may be found below.  We hope to see … Continue reading

Update on Construction: Making Steady Progress

Hi Folks – Overall, the project is now about 30% complete.  Recently, the construction crew has been busy working on the new retaining walls for the tennis courts.  Soon, you can expect to see more grading as we start to construct the new tennis courts. The contractor has also been hard at work inside … Continue reading

Glen Canyon Park Project – April Update

Hi Everyone, Over the last few weeks and in the coming weeks, work will continue on the grading and building the new retaining walls for the new tennis courts.  In addition, work is underway inside the Rec Center to prepare for the installation of the much-anticipated, new heating system. Again, there is some large equipment on … Continue reading

Glen Canyon Park Renovation: Progress update – work proceeding…

Construction started in early January and is progressing steadily.  When complete, the project will feature improvements to the tennis courts, children’s play area, recreation center, landscaping, and Elk Street entrance. To date, the tennis courts and their surrounding retaining walls, as well as the old children’s play equipment have been … Continue reading

Glen Canyon Park Renovation Project Underway!

Hi folks, As you might have noticed, starting last week, the renovation project is underway!  The project is anticapated to be completed in November of 2013, assuming no additional delays. As a reminder, major improvements include: a new children’s play area that will be almost twice as large as the … Continue reading

FYI – Other work in park, trail improvements north of Rec Center, along “Saddle Area”

Hi folks, Just in case you notice and were wondering, there will be some work on one area of the trails in Glen Canyon Park, north of the rec center, called the “saddle area”  It is north of the boardwalk and near the climbing rocks.  It will see improvements beginning January 15, … Continue reading

Construction to Start on Glen Canyon Park Renovation Project – Portions of the Park Around Elk Street Closed Stating January 10th, other portions closed starting the week of January 14th

Hi Everyone – The contractor hired to start the Glen Canyon Project will be starting construction activities Thursday, January 10th.  At times, on  Thursday January 10th and January 11th, and the week of  January 14th tennis courts may be closed in order to protect park users during some work. It … Continue reading

Update on Glen Canyon Project, CEQA Appeal Found Untimely and Upcoming Project Update Meeting, January 7th

GlenPark Renovation Project – Project Update Meeting 1 7 13 Greetings and happy holidays from the Recreation and Park Department! We are looking forward to starting park renovation project at Glen Canyon Park. As you may have heard, the schedule has been delayed from the original start date of October … Continue reading

Glen Canyon Renovation Project Update – Rehearing Request on Building Permit Appeal Withdrawn and CEQA appeal filed

Hi Everyone, Another update - the appellant withdrew their re-hearing request today, so there is no hearing tonight, I am very sorry if you got this news too late, and already left for City Hall.  I heard late in the day myself.  The appeals board ‘s vote of 4-0 to deny the appeal, is now … Continue reading

Update on Building Permit Rehearing Request on Glen Park Renovation – Scheduled for December 12th

Hi Everyone, Here is the latest update: As you know, the appeals board voted 4-0 to deny the appeal on November 14th. The appellant had a 10 day period to file a re-hearing request. The last to file this request was November 26th. On that date, the appellant submitted a … Continue reading

Update – Glen Canyon Project, Building Permit Appeal, Re-Hearing Request Filed

Hi Everyone, Quick update about the appeals process. As you know, the appeals board voted 4-0 to deny the appeal, but the appellant had a 10 day period to file a re-hearing request. The last to file this request was November 26th. On that date, the appealant submitted a re-hearing … Continue reading

Project Delayed – Appeal Filed on Building Permit – Update Soon!

Hello Everyone – As we have planned and communicated in flyers and elsewhere, we were planning on starting construction in mid October, this week on this project. However, on Monday an appeal was filed on the building permit that had been issued for the project. The permit and the project … Continue reading

Glen Canyon Park Renovation Update and Additional Information on Tree Work and Recent Tree Failures

Hi everyone, As you may know, the Glen Canyon Park Renovation Project will begin soon! As a reminder, major improvements include: a new larger children’s play area, new tennis courts, improved park paths, an improved Elk Street entry, a new accessible restroom, new landscaping, and new heating in the Recreation … Continue reading

Update on Glen Canyon Park Renovation, Notices of Tree Removals and New Tree Planting Information

As part of the upcoming Park Renovation Project, today a number of trees around the lower portion of Glen Canyon Park were posted with notices that the tree will be removed as part of the renovation. As a reminder, this project, which came out of a two year community planning … Continue reading

Glen Canyon Park/Playground Improvements – Getting Contractor On Board

Apologies for our blog-writing hiatus! We’ve been busy finishing the design drawings for what is certain to be a fantastic renovation of Glen Canyon Park. Right now, we are completing the bid of the construction contract to a qualified construction company. We are on schedule to start construction on October. … Continue reading

Thank you for your continued interest and participation in the renovations at Glen Canyon Park

Thank you for your continued interest and participation in the renovations at Glen Canyon Park—from attending community meetings to emailing your thoughtful comments. The completion of a series of productive and informative community meetings marks the end of the planning stage of the Glen Canyon Park Renovation project. The project … Continue reading

Thanks For Attending Saturday’s Final Community Design Meeting on Glen Canyon! See Below For More Information

Thank you to all who attended Saturday’s community meeting! We had a good turnout, and we received a lot of helpful feedback, which will continue to inform us as we move forward with the Glen Canyon Park renovation. For those of you who were unable to join us on Saturday, … Continue reading

Reminder: Next Saturday, December 10th – Glen Canyon Park Community Meeting on Bond Project

Glen Canyon Park Community Meeting Learn about the proposed improvements! Come give us your input! Saturday, December 10, 2011 3 p.m. – 5 p.m. At Glen Canyon Park Recreation Center (located inside the park, near the intersection of Elk & Chenery Streets) Come to the latest community meeting we are … Continue reading

Reminder: Glen Canyon Park Community Meeting on Park/Playground Renovation Next Saturday, Nov. 12th!

The November 12th Community Meeting to discuss Glen Canyon Park’s renovation is just around the corner! We hope you can join us to check out the park’s new design and share your preferences for new playground equipment! Thanks to all for coming to the series of community meetings we had … Continue reading

Come to the Glen Canyon Park Project Meeting – November 12th – See Below for More details!

Glen Canyon Park Join us! Come give us your input! Thanks to all for coming to the series of community meetings we had to identify top priorities for improvement to Glen Park. In the last meeting held this summer, we presented those items proposed for renovation with the Clean and … Continue reading

Glen Canyon Park Project Next Steps: Info about Fall meeting coming soon!

Hi Everyone – We are excited to report that the Recreation and Parks Commission voted to recommended that the Board of Supervisors accept the Trust for Public Land’s gifted services and improvement plan for Glen Canyon Park at their August 18th meeting, and directed RPD Staff and the design team … Continue reading

Next Steps for Glen Canyon Park Improvement Plan and Future Meeting Planned on Playground Design

Hi folks! As we announced at the last meeting, we will be headed to the Rec Park Commission this month to accept the gift of the improvement plan provided by Trust for Public Land and start the process of the final community outreach and design for the first -funded! – … Continue reading

Reminder: Final Presentation and Reminder for Celebration Tonight!

Please join us to for the final presentation for the Glen Canyon Park Improvement Plan on Thursday, June 9th, 6:30-8:30pm at the Glen Canyon Recreation Center. After nine community workshops, a guided trail walk, several focus groups, meetings with city agencies and departments, and countless email and mail feedback from … Continue reading

Glen Canyon Park Workshop 5/5 6:30-8:30pm

Dear Glen Canyon Park Community, The 2008 Clean and Safe Neighborhood Parks Bond dedicated $5.8 million to improving Glen Canyon Park. SF Recreation & Parks (RPD) is partnering with The Trust for Public Land (TPL) to design and prioritize a park improvement plan at Glen Canyon Park. We will be … Continue reading

We want your feedback on conceptual design options for the Glen Canyon Park Improvement Plan!

Dear Glen Canyon Park Stakeholders and Enthusiasts: We want your feedback on conceptual design options for the Glen Canyon Park Improvement Plan! The Trust for Public Land (TPL) is partnering with SF Recreation & Parks to vision and design a Park Improvement Plan for Glen Canyon Park. At the community … Continue reading