Updates on Palega Recreation Center

Palega Recreation Center is still under construction having opened 4 months ago. Palega Rec is currently closed from 03/26/2014 – 03/27/2014 for Open Gym for  floor repair. We will re-open on Friday 03/28/2014. While the gym is closed feel free to come in and enjoy our outdoor facility, various multi-purpose rooms, or our indoor … Continue reading

Palega Recreation Center Reopens After $21.2 Million Renovation

SAN FRANCISCO— The San Francisco Recreation and Park Department and city officials, including Supervisor Malia Cohen, joined hundreds of Portola District friends and neighbors today in celebrating the reopening of Palega Recreation Center, a neighborhood favorite. The 80-year-old park and recreation center recently underwent a $21.2 million makeover, thanks to … Continue reading

Palega Playground Renovation _ update

Project is 92% complete, we are now entering the final phases of work; Gym interior painting is ongoing, Gym floor is currently being installed, all toilet & bathroom fixtures are complete, interior radiators are substantially complete. New storefront windows are being installed at the addition, wrapping up miscellaneous roof installation. … Continue reading

Palega Construction Progress_ Project update

Project is approximately 72% complete. Progress continues on the Palega Improvements, including window flashing, exterior stucco. On the interior, contractor is proceeding with sheetrock and taping, storefront windows prep work, casework, mechanical registers, radiant piping are proceeding. Site work is also ongoing, including main lines, irrigation, underground utilities and fencing. Structural steel … Continue reading

Palega Construction_Progress Continues Feb 2013

Project is 65% complete. Contractor continues to make progress on duct work, wall framing, exterior sheating and wall insulation. Steel window repairs are also ongoing. Plaster repairs are also underway on the exterior. The strutural steel work is proceeding on the addition, contractor is also prepping tp pour structural slab … Continue reading

Palega construction continues_ Jan 2013

After a very wet winter December, construction crews are mobilized fully for the week starting Jan 7th 2013. Project is 55% complete. Seismic work in the Gym continues, roofing at the upper level is substantially complete. Hydronic heating installation have commenced, rough electric and plumbing is ongoing, Fire sprinkler installation … Continue reading