Geneva Community Garden Contract Award Approval Scheduled for December Commission

Bids from 5 interested contractors were received on November 8, 2016 for the Geneva Community Garden project. Today, on November 23, tentative award of contract was sent to GECMS, Incorporated. Please join us for the Rec and Park Commission Capital Committee hearing on Wednesday, December 7 to support the award … Continue reading

Geneva Community Garden Rebid to Contractors

The Geneva Community Garden project has been simplified and re-advertised to contractors. Interested A and C-27 contractors can view the solicitation here. The contractor that withdrew his bid from the first round back in May will be prohibited from submitting a bid for this second round.  A pre-bid conference was held on site … Continue reading

Geneva Community Garden Still in Progress

Thank you for your patience as the creation of a community garden at Geneva Ave and Delano has taken longer than anticipated. Environmental remediation was lengthier and more expensive than expected but has been completed. To supplement original funding, Rec and Park pursued and secured additional grant funding of $900,000 from two state Housing Related Parks … Continue reading

Geneva Community Garden Construction Contract Advertised to Contractors

The Geneva Community Garden project was advertised to contractors earlier this month. A pre-bid conference was held on site and bids are due on May 10. Interested contractors can find the advertisement here: http://mission.sfgov.org/OCABidPublication/BidDetail.aspx?K=10781 Following bid due date, we will work to review bids and award contract as soon as possible … Continue reading

Final Bid Package Prep Underway for Geneva Community Garden Project

We are in the final stages of preparing to advertise the Geneva Community Garden construction project to contractors. Thank you for your patience as we were recently dealing with extended leave of a couple of our project team members. We are also in the process of coordinating with other City agencies … Continue reading

Geneva Community Garden Construction Coming in 2016!

Thanks to project supporters and neighbors for your patience. We anticipate advertising the Geneva Community Garden construction project to contractors in February 2016 and starting construction by summer 2016 for completion and opening before the end of the year. Project delay is due mostly to tight funding, which has had … Continue reading

Update on Progress for Future Geneva Community Garden

Environmental remediation at the site has been completed.  Rec and Park was awarded a second Housing Related Parks Grant this year, which is a tremendous help since environmental remediation costs were higher than anticipated. Target schedule is as follows: Advertise to contractors: fall 2015 Begin construction: winter 2016 Open garden: late … Continue reading

Geneva Community Garden Phase I Construction to begin in April

We anticipate that construction for Phase I of the new Geneva Community Garden will begin this April.  Flyers showing the concept plan for the garden were posted on site last week.  Construction is estimated to last approximately 4 months.  First up will be removal of the 2 pines that have … Continue reading