Schedule Update and Phased Reopening

Completion of the lawn installation is a major project milestone that now offers a more definitive picture of the project schedule. As of mid-November we are anticipating that the new viewing area will open shortly after the New Year at the same time that the original viewing area closes. Irrigation and grading … Continue reading

A New Lawn for Alamo Square!

Following last week’s tree planting, new sod is now being installed at Alamo Square. The hillside along Scott Street is the first area to receive a “no mow” fescue grass, which will be used on steeper slopes throughout the park to create a naturalized landscape. When established, this grass will … Continue reading

Trees are being planted at Alamo Square!

The Alamo Square Neighborhood Association (ASNA) has provided a generous gift of 45 new trees that are being planted at Alamo Square this week.  ASNA is also funding the planting of approximately 30 additional trees that will be installed in 2017 alongside the Recreation and Park Department’s new drought-tolerant tree, shrub, … Continue reading

Alamo Square Construction Update!

Hello! I’d like to introduce myself as the new Project Manager for the Alamo Square Restroom and Irrigation Upgrade Project. As of mid-September we are approximately 50% of the way through the $4.3 million renovation project. The contractor has nearly completed the installation of the modern, water-efficient, irrigation system that will save … Continue reading

REMINDER: Alamo Square Park

Alamo Square Park is closed for renovation until fall/winter 2016. Chain link fence panels are installed around the entire park perimeter. Please do not enter the construction for your own safety. If you observe someone trespassing or an opening along the perimeter, please contact 311. Thank you for your patience … Continue reading

TEMPORARY CLOSURE ADVISORY: Alamo Square

Alamo Square will close on May 10 (Tue) to undergo a park-wide irrigation system replacement, construction of a new wheelchair-accessible restroom, and installation of new landscaping. Alamo Square will remain close for seven months, and is expected to reopen in fall/winter 2016. This $4.3M project is made possible by the Restroom … Continue reading

UPDATE: Alamo Square Renovation

In preparation for the Alamo Square restroom and irrigation upgrade project, the Recreation and Park Department is performing the removal of up to 14 trees which have been evaluated as hazards or declining in health. This work will occur after March 8 when Alamo Square is fenced for construction. To minimize … Continue reading

UPDATE: Timeline and Scope of Work

Alamo Square Park will undergo a $4.3 million renovation to update the irrigation system, build an ADA-accessible restroom, and landscape the entirety of the park. The outcome of the project will result in water savings through improved irrigation design, the installation of “smart” controllers, and the planting of lawn alternatives, … Continue reading

UPDATE: Alamo Square Restroom and Irrigation Project

The Recreation and Park Dept. received 5 bids in mid-December for the Alamo Square Restroom and Irrigation Project. The lowest 2 bids are within the City’s construction budget. Currently the City is reviewing the bids for qualifications and anticipates making a recommendation for contract award in February. Construction is anticipated to … Continue reading

Alamo Square Improvement Project – Construction Update!

We are excited to announce that we are getting ready to go into construction! Thanks again to San Francisco Voters who overwhelmingly supported the 2008 and 2012 Clean and Safe Neighborhood Parks Bond, without your support this project would not be possible. We are going to be completing the project … Continue reading