Glen Canyon Park Recreation Center Renovation Community Meetings

Hi Everyone! As many of you may know, thanks to the community planning process in 2010-2011 which identified the needs for renovation and improvement of the facilities at Glen Canyon Park, not only is the playground and tennis court renovation in construction now, the Recreation Center Renovation was funded by … Continue reading

Recreation Center Renovation – Community Meeting Planned for June, Date to be Finalized Shortly!

Hi Everyone- With the renovation of the Glen Canyon Park playground, tennis courts, and Elk Street entryway well underway, we are beginning to plan for the renovation of the Glen Canyon Park recreation center, funded by the 2012 Clean and Safe Neighborhood Parks Bond. The Glen Canyon Park Recreation Center … Continue reading

Update on Construction: Making Steady Progress

Hi Folks – Overall, the project is now about 30% complete.  Recently, the construction crew has been busy working on the new retaining walls for the tennis courts.  Soon, you can expect to see more grading as we start to construct the new tennis courts. The contractor has also been hard at work inside … Continue reading

City Scores Victory for Kids, Soccer

Great news! The California Coastal Commission voted unanimously today to uphold the permit for the Beach Chalet Athletic Field renovation project at the West End of Golden Gate Park, perhaps the most vetted public project in Rec and Park history. The Commission’s vote means the renovation project can move forward … Continue reading

Palega Construction Progress_ Project update

Project is approximately 72% complete. Progress continues on the Palega Improvements, including window flashing, exterior stucco. On the interior, contractor is proceeding with sheetrock and taping, storefront windows prep work, casework, mechanical registers, radiant piping are proceeding. Site work is also ongoing, including main lines, irrigation, underground utilities and fencing. Structural steel … Continue reading

Mission Pool Improvements_2nd Phase commences

The Pool locker room work (first phase) is substantially complete. (see attached pics) The second and final  Phase of the Pool Improvements have commenced. Demolition of the existing concrete slab is complete. Contractor is now trenching for new slot drains and new main drains. A brand new pool recirculation piping and pump … Continue reading

Glen Canyon Park Project – April Update

Hi Everyone, Over the last few weeks and in the coming weeks, work will continue on the grading and building the new retaining walls for the new tennis courts.  In addition, work is underway inside the Rec Center to prepare for the installation of the much-anticipated, new heating system. Again, there is some large equipment on … Continue reading

Mission Pool Improvements_ Progress continues

The first phase of the work (Pool Locker Room Improvements) is approximately 75% complete and it is expected to be complete by Mid  March so that the Pool Deck and systems can commence right away.Tile work is ongoing, fixture installation will commence next, interior to follow afterwards. Exterior stucco work will … Continue reading

Palega Construction_Progress Continues Feb 2013

Project is 65% complete. Contractor continues to make progress on duct work, wall framing, exterior sheating and wall insulation. Steel window repairs are also ongoing. Plaster repairs are also underway on the exterior. The strutural steel work is proceeding on the addition, contractor is also prepping tp pour structural slab … Continue reading

Glen Canyon Park Renovation: Progress update – work proceeding…

Construction started in early January and is progressing steadily.  When complete, the project will feature improvements to the tennis courts, children’s play area, recreation center, landscaping, and Elk Street entrance. To date, the tennis courts and their surrounding retaining walls, as well as the old children’s play equipment have been … Continue reading

Community Message at Open House: Happy Our Plan is Moving Forward, Please Manage Construction Carefully

After nearly a year of environmental review, the community members attending the Mission Dolores Park Rehabilitation Project Open House were happy to see the design is moving forward with few changes.   They also pointed out that the next challenge is publicizing and managing the construction process to minimize disruption of … Continue reading

Dolores Park Project Open House Wed. Feb. 6, 5:30-7:30PM

In the last year, the Mission Dolores Park Rehabilitation Project has moved forward through environmental review and documentation.  The project team is now ready to share the updated plans with you and the entire park community. Please join us for a Community Open House this Wednesday, February 6th from 5:30-7:30 … Continue reading

Glen Canyon Park Renovation Project Underway!

Hi folks, As you might have noticed, starting last week, the renovation project is underway!  The project is anticapated to be completed in November of 2013, assuming no additional delays. As a reminder, major improvements include: a new children’s play area that will be almost twice as large as the … Continue reading

FYI – Other work in park, trail improvements north of Rec Center, along “Saddle Area”

Hi folks, Just in case you notice and were wondering, there will be some work on one area of the trails in Glen Canyon Park, north of the rec center, called the “saddle area”  It is north of the boardwalk and near the climbing rocks.  It will see improvements beginning January 15, … Continue reading

Construction to Start on Glen Canyon Park Renovation Project – Portions of the Park Around Elk Street Closed Stating January 10th, other portions closed starting the week of January 14th

Hi Everyone – The contractor hired to start the Glen Canyon Project will be starting construction activities Thursday, January 10th.  At times, on  Thursday January 10th and January 11th, and the week of  January 14th tennis courts may be closed in order to protect park users during some work. It … Continue reading

Palega construction continues_ Jan 2013

After a very wet winter December, construction crews are mobilized fully for the week starting Jan 7th 2013. Project is 55% complete. Seismic work in the Gym continues, roofing at the upper level is substantially complete. Hydronic heating installation have commenced, rough electric and plumbing is ongoing, Fire sprinkler installation … Continue reading

Update on Glen Canyon Project, CEQA Appeal Found Untimely and Upcoming Project Update Meeting, January 7th

GlenPark Renovation Project – Project Update Meeting 1 7 13 Greetings and happy holidays from the Recreation and Park Department! We are looking forward to starting park renovation project at Glen Canyon Park. As you may have heard, the schedule has been delayed from the original start date of October … Continue reading

NEN Awards: Help McLaren Park Wins Award

The Neighborhood Empowerment Network’s NEN Awards are returning for their fifth and biggest year on January 9. Produced in partnership with the CCSF Community Challenge Grant Program, The NEN Awards are dedicated to elevating and celebrating the tremendous work that residents and organizations do every day to make our city … Continue reading

Glen Canyon Renovation Project Update – Rehearing Request on Building Permit Appeal Withdrawn and CEQA appeal filed

Hi Everyone, Another update - the appellant withdrew their re-hearing request today, so there is no hearing tonight, I am very sorry if you got this news too late, and already left for City Hall.  I heard late in the day myself.  The appeals board ’s vote of 4-0 to deny the appeal, is now … Continue reading

Update on Building Permit Rehearing Request on Glen Park Renovation – Scheduled for December 12th

Hi Everyone, Here is the latest update: As you know, the appeals board voted 4-0 to deny the appeal on November 14th. The appellant had a 10 day period to file a re-hearing request. The last to file this request was November 26th. On that date, the appellant submitted a … Continue reading

Update – Glen Canyon Project, Building Permit Appeal, Re-Hearing Request Filed

Hi Everyone, Quick update about the appeals process. As you know, the appeals board voted 4-0 to deny the appeal, but the appellant had a 10 day period to file a re-hearing request. The last to file this request was November 26th. On that date, the appealant submitted a re-hearing … Continue reading

Project Delayed – Appeal Filed on Building Permit – Update Soon!

Hello Everyone – As we have planned and communicated in flyers and elsewhere, we were planning on starting construction in mid October, this week on this project. However, on Monday an appeal was filed on the building permit that had been issued for the project. The permit and the project … Continue reading

Glen Canyon Park Renovation Update and Additional Information on Tree Work and Recent Tree Failures

Hi everyone, As you may know, the Glen Canyon Park Renovation Project will begin soon! As a reminder, major improvements include: a new larger children’s play area, new tennis courts, improved park paths, an improved Elk Street entry, a new accessible restroom, new landscaping, and new heating in the Recreation … Continue reading

Dolores Park Rehabilitation and Improvement Project Open House Rescheduled

The Dolores Park Rehabilitation and Improvement Project Open House, previously scheduled for Thursday, September 27,  has been rescheduled to a date to be announced later this fall. The Rehabilitation and Improvement Plan is progressing through the Planning Department’s environmental review process. This is taking a little longer than expected, so … Continue reading

Update on Glen Canyon Park Renovation, Notices of Tree Removals and New Tree Planting Information

As part of the upcoming Park Renovation Project, today a number of trees around the lower portion of Glen Canyon Park were posted with notices that the tree will be removed as part of the renovation. As a reminder, this project, which came out of a two year community planning … Continue reading

MISSION PLAYGROUND & CLUBHOUSE RIBBON CUTTING EVENT

Please join us for the Mission Playground and Clubhouse ribbon cutting ceremony on Saturday, September 15th at 10:30am. Thanks to SF voters the park was renovated with funds from the 2008 Clean & Safe Neighborhood Parks Bond.  The renovation includes a renovated clubhouse and new playground including an exciting water feature, new synthetic turf soccer field, resurfaced … Continue reading

Mission Dolores Park Project Progressing through Planning Department Reviews; Project Open House Announced for Thursday, September 27th

The Mission Dolores Park Rehablitation and Improvement Plan is progressing through the Planning Department’s environmental review process. In addition, a peer review of the historical evaluation process is also taking place. To keep everyone posted on the project’s progress and answer any questions that have come up, we have scheduled … Continue reading

Construction Phase Community Briefing, Wednesday August 1

Park neighbors, visitors and other interested stakeholders are invited to attend a special meeting on Wednesday, August 1st, during which project staff will provide an update on the progress of the work as well as an overview of what is to come. Details are provided below.  We hope to see you there. Lafayette Park Renovation, Community Briefing Wednesday, August 1 – … Continue reading

Glen Canyon Park/Playground Improvements – Getting Contractor On Board

Apologies for our blog-writing hiatus! We’ve been busy finishing the design drawings for what is certain to be a fantastic renovation of Glen Canyon Park. Right now, we are completing the bid of the construction contract to a qualified construction company. We are on schedule to start construction on October. … Continue reading

Planned Construction Activities – May and June 2012

May is drawing to a close and the harbor renovation has seen spectacular in-water progress over the last month, while the landside work has limped along.  Work interruptions, material delivery delays, and over optimism has become the norm for work on the harbormaster building.  As the month draws to a … Continue reading

NEW Marina Policies.

The Recreation and Park Commission has adopted new policies for the management and operation of the San Francisco Marina Small Craft Harbor.  New Marina Rules & Regulations were adopted on April 19, 2012, which are now in effect.  Also, the Commission adopted a Post-Renovation Berthing Assignment Policy for the repopulation … Continue reading

Planned Construction Activities – April 2012

Phase 2 in-water construction is currently underway.  The Contractor completed demolition or C and E Docks [those accessed off the West Mole] during the first two weeks of April.  Intense construction activities in the vicinity of the West Mole will continue throughout the month.  Work in the area will include … Continue reading

Helen Diller Playground at Mission Dolores Park Now Open!

San Francisco Recreation and Park Department (RPD) announced today the grand opening of Helen Diller Playground in Mission Dolores Park. Mayor Ed Lee, Supervisor Scott Wiener, San Francisco Recreation and Park Department, Mrs. Helen Diller and family, San Francisco Parks Alliance, Friends of Dolores Park Playground, and park advocates gathered … Continue reading

New Marina Rules, Regs, and Policies posted to the department website.

The proposed Post-Renovation Berthing Assignment Policy for the Marina West Basin and the proposed new Marina Rules and Regulations have been posted on the sfrecpark website for public review. Also, you will find the Notice of the Public Hearing pertaining to this matter and the Community Feedback Report that encapsulates the … Continue reading

Construction Contract Awarded for Lafayette Park Renovation

The Recreation and Park Commission took action today to award the construction contract for the Lafayette Park Renovation project to Bauman Landscape and Construction.  Bauman has successfully delivered a number of park renovation projects, including the lovely Sue Bierman Park and the soon to be unveiled Helen Diller Playground in … Continue reading

Planned Construction Activities – March 2012

March is set to be an exciting month in the Marina.  Beginning March 17, the first lot of newly constructed docks and slips will be opened for boat occupancy.  During the course of the last two weeks of the month, the Harbormaster will begin directing boaters toward new, temporary slips … Continue reading

Opening Celebration on March 31st!

You are cordially invited to join Mayor Edwin M. Lee, Supervisor Scott Wiener, San Francisco Recreation and Park Department General Manager Phil Ginsburg, Mrs. Helen Diller, San Francisco Parks Alliance and Friends of Dolores Park Playground for the grand opening ceremony of Helen Diller Playground at Mission Dolores Park on … Continue reading

Complete Mission Dolores Park Rehabilitation Plans Enthusiastically Received at Open House

At a Wednesday night Open House, the Dolores Park community gave the complete Mission Dolores Park Rehabilitation Plans two thumbs up–for accurately representing all the community’s decisionmaking and for bringing together everyone’s ideas into a beautiful design.   Community members also provided dozens of comments confiming their support and suggesting further refinements. … Continue reading

Welcome to the Restroom Repair & Renovation Program News

The Restroom Repair and Replacement program funds the construction, repair, and renovation of restroom facilities. Many of the city park’s restrooms are old, need repair and are poorly designed for maintenance and proper supervision. Following the passage of the 2008 Clean & Safe Neighborhood Park Bond, the Recreation & Parks … Continue reading

Mission Dolores Park Rehabilitation Plan Open House: Opportunity to Review Complete Plan and Construction Calendar

On Wednesday, February 29th everyone in the Dolores Park community will have an opportunity to review the complete park rehabilitation plan and the proposed construction calendar.   Please join us at the Mission High School Cafeteria at the corner of 18th St. and Dolores St. anytime between 5:30 and 8:30PM on the evening on of the 29th.  The location is … Continue reading