50% of Helen Diller playground project done

The project is 50% complete, contractor is proceeding with concrete flatwork, including curbs and walls. In addition irrigation lateral lines are being installed. Anticipating the delivery of the bridge in mid January, play equipment is scheduled to start arriving thereafter. Project will be open to the public in Spring 2012.