Balboa Park Pool Improvement Project

Balboa Pool

Construction begins October  31st 2016!

Once the renovation at Balboa Pool is completed in Fall 2017, the $11 million Garfield Pool renovation and $8.2 million Rossi Pool renovation will follow. The three renovations will not overlap in an effort to serve the public with as much aquatic recreation as possible.

PROJECT SCOPE

The project may include the renovation of the pool, pool building, the potential addition of an 800 square foot multi-purpose space, and the site improvements to related amenities.

Anticipated Start Date:  September/October 2016
Anticipated Completion Date:  Fall 2017

Funding Source

The project has been allocated $7 million from the 2012 Clean and Safe Neighborhood Parks Bond.

DESCRIPTION

Balboa Park and Pool are located at 511 Havelock Street at San Jose at San Jose and Ocean Avenues. The approximately 1.1.million square foot park has multiple fields for soccer and baseball, tennis and basketball court’s, a children’s play area, skateboard park and a pool.

Balboa Pool Renovation – Construction Update

The Recreation and Park Department is undertaking a renovation project at Balboa Pool. The project commenced in November 2017, and is approximately 60% complete. The contractor is making good progress and the department currently anticipates re-opening the facility in early 2018. Work Occurring this Month: Preparing the pool for new … Continue reading

Balboa Pool Construction Update!

The project is approximately 22% complete. In terms of progress, the months of January and February has been a very wet one, thus slowing down considerable the progress of work in the past few weeks. This has impacted the contractor’s ability to perform some of its planned activities. Fortunately this … Continue reading

Introduction, Tree Removal & Construction Update

Hello! I’d like to introduce myself as the interim project manager for the Balboa Pool renovation while Levi Conover is on leave. As many neighborhood residents have likely noticed, there was significant damage to the grove of trees at the corner of Havelock Street and San Jose Avenue caused by Tuesday’s storm. As … Continue reading

Balboa Pool Construction has Begun!

Once the renovation at Balboa Pool is completed in Fall 2017, the $11 million Garfield Pool renovation and $8.2 million Rossi Pool renovation will follow. The three renovations will not overlap in an effort to serve the public with as much aquatic recreation as possible.

Balboa Pool Nearing Construction!

Within the next few weeks contractors will be moving onsite and will be staging at the basketball  courts, which will remain closed for the duration of construction due to safety concerns as the building gets seismically retrofitted, and the renovated. Thank you for your patience!

Balboa Pool, Nearing Construction!

We are excited to announce that we received a responsive bid for the Balboa Pool Renovation which will allow us to move forward with the implementation of the project as envisioned. The name of the contractor is CLW Builders. They have worked with on numerous Rec Park Projects that include the … Continue reading

Balboa Pool Construction Update

Unfortunately, the Balboa Pool project bids all came in over our budget. This continues to be a challenging bidding environment on all fronts, including  material cost increases, competition for labor and a very hot market for builders. We are re bidding the project now and bids will be received in … Continue reading

Visit the Archives