Progress continues at Mission Dolores Playground

Project is 65% complete . Boulder walls were delivered to the site and are being placed in their final destination. The granite climbing walls have also being placed. Irrigation lateral lines are continuing at mow-band, including setting of valve boxes. Backfill and grading is ongoing at climbing wall.

 The south abutment walls were formed and have been poured  in addition the lower playground walls and play-mound walls will be poured also. The rest of the flat work is scheduled for first week in January.

Soil amendment and application of fertilizer is also ongoing throughout the site.

Forming cheek-walls at amphitheatre, curved walls at large slide, stepped retaining wall at 2 tier bolder wall. Sand table was installed this week also

Electrical conduit installation including pull boxes are ongoing within playground.