Planned Construction Activites: May 30-June 17

Below is a forecast of the upcoming construction activities related to the West Harbor renovation project:

Weeks of May 30 and June 6:  Mobilization of the dredging barge and floating equipment barge,  utility capping and demolition of vacated docks along the north jetty and west of the Scott Street mole, and the pulling of piles remaining after dock demolition.

Week of June 13:  Dredging begins in the entrance channel and in the areas where docks have been removed.

On-going:  Relocation of vessels in the planned 2011 work areas is underway.  Vessels remaining along Sail Boat row will be relocated during June.