Palega Improvements _unto Final Phase

Project is 87% complete, site work ongoing, including forming and pouring for new sidewalks. The radiant flooring at the new addition have been poured. Metal windows are in. Exterior stucco work is ongoing. Interior wall finish at the gym is ongoing including painting. On the exterior, irrigation and infield work have commenced. Underground utilities connection are also ongoing. Site wall foundation are being formed for concrete pour in the next 2 week. Sod installation is also imminent.