Palega Construction_Progress Continues Feb 2013

Project is 65% complete. Contractor continues to make progress on duct work, wall framing, exterior sheating and wall insulation. Steel window repairs are also ongoing. Plaster repairs are also underway on the exterior. The strutural steel work is proceeding on the addition, contractor is also prepping tp pour structural slab by 2nd week of March barring rains. On the site work contractor is continuing with concrete pathway work, additional regrading of site and site fencing.