Palega Construction Construction Update (May 2013)

Project is 82% complete, site work is ongoing, including forming and pouring for
new sidewalks. Transformer pad for PG&E is being poured, grading and
Irrigation is also proceeding. In the addition, prep work for radiant flooring have
commenced. Exterior upper new  windows are complete, stucco repair work is
ongoing. On the interior, glass partition installation have commenced, tile
work in the interior restrooms, sheet rock and taping of the walls are also
ongoing.