Palega Construction Progress_ Project update

Project is approximately 72% complete. Progress continues on the Palega Improvements, including window flashing, exterior stucco. On the interior, contractor is proceeding with sheetrock and taping, storefront windows prep work, casework, mechanical registers, radiant piping are proceeding. Site work is also ongoing, including main lines, irrigation, underground utilities and fencing. Structural steel work continues on the addition, concrete slab has also being poured for the addition.