Palega construction continues_ Jan 2013

After a very wet winter December, construction crews are mobilized fully for the week starting Jan 7th 2013. Project is 55% complete. Seismic work in the Gym continues, roofing at the upper level is substantially complete. Hydronic heating installation have commenced, rough electric and plumbing is ongoing, Fire sprinkler installation is ongoing, including duct work installation. Steel erecttion is also ongoing at new addition. Contractor is also forming and pouring stemwalls at the new addition. Pending more dry weather, site irrigation is also scheduled to commence during the week of 1/14/13.