Oak Woodlands Trails Improvement Project Schedule

Site visit

The target timeline that we posted late last year was to complete construction documents and advertise to contractors sometime this summer.  Please see updated anticipated project schedule below.  The largest reason for the updated timeline is that our landscape architect was unexpectedly out on leave for several months; however, there are some other factors.  We are having another tree assessment done and are planning to complete another round of hazard tree abatement in the fall, ahead of the general contract scope, to make the rest of the scope easier to complete and also to minimize conflict between bird nesting and tree work.  We also want to avoid starting work right in the middle of the rainy season to avoid costly delays and to help maximize appeal to quality contractors. Finally, the construction duration is a bit longer than we originally anticipated, but that is to allow for planting at a more appropriate time, at the end of the project.

Advertise project to contractors                                November 2017

Contract award to Commission                                February 2018

Notice to Proceed / Construction Start                    March 2018

Construction substantial completion                       December 2018

(9 month construction duration)

For those interested in more background info and details, please see copy of a presentation that we gave to a neighborhood group back in July by clicking here.

Thanks for your patience.  We are definitely making progress and are excited to make even more in the near future!  If you have questions or comments, please reach the Project Manager at melinda.stockmann@sfgov.org  or 415-581-2548.