Mayor Ed Lee along with Supervisors’ Breed, Farrell, and Tang visited the site on 11/05/14 and were able to see first-hand progress of work, which is now at 35% completion.

Trench drains are complete, concrete curbs are complete, irrigation, sand catchers and D Zone prep work is ongoing.

Kezar Track_photo of gutter installation

Kezar Track_photo of base of track

 

 

 

 

 

Next steps: Contractor will commence on asphalt leveling work during the first week of December.