Kezar Track Improvements Update 10-7-14

Kezar Track Demo_01

The following has occurred onsite since the contractors mobilization on September 30th:

– Temporary barriers are in place to secure the site;

– Removal of the old track is substantially complete; (See attached pictures)

– Additional Demo is ongoing; and

– Mondo Submittal Review for the new track is ongoing.

Kezar Track Demo_03Kezar Track Demo_02Kezar Track Demo_04